10 March, 2015
09 March, 2015
06 March, 2015
06.03.15
SITE SITUATION TODAY -VIEW
FROM EAST
ARRIVAL OF 20T HAMMER FOR DYNAMIC TEST ON PILES DIAM 1200mm
PILE DYNAMIC TEST PDA ON TP-B01 1200mm DIAM
PILE DYNAMIC TEST PDA ON TP-B03 1200mm DIAM
PILE DYNAMIC TEST PDA ON TP-B06 1200mm DIAM
MAINTAINED LOAD TEST ON TP-B18 IN PROGRESS
PREPARATION OF COUNTER WEIGHTS FOR MLT ON TP-B03
PREPARATION WORK FOR AXIAL TENSILE LOAD TEST ON TP-B04
CONCRETING OF THE LAST MC’S TEST PILE
CONSTRUCTION OF SITE BATCHING PLANT IN PROGRESS
05.03.15
SITE SITUATION TODAY -VIEW
FROM EAST
ALSTOM MANAGEMENT SITE VISIT
AXIAL TENSILE LOAD TEST ON TPB13 ONGOING
TENSILE LOAD TEST ON TPB13 – HONEY BOX
MAINTAINED LOAD TEST ON TPB15 IN PROGRESS
TPB15 - HYDRAULIC JACKS UNDER REACTION GIRDER
PREPARATION WORK ON TPB18 FOR MAINTAINED LOAD TEST
PILING WORK FOR MC’S TEST PILES
FENCING AT SOUTH-WEST SIDE WILL BE CONTINUED AFTER LAND RECLAMATION
CONSTRUCTION OF SITE BATCHING PLANT BY CPAC ON GOING
03.03.15
SITE VIEW FROM SOUTH
WEEKLY SAFETY INDUCTION CONTINUE REGULARLY EVERY TUESDAY
PREPARATION WORK FOR AXIAL TENSILE LOAD TEST ON TPB13
TPB15 READY FOR MAINTAINED LOAD TEST
START OF MAINTAINED LOAD TEST ON PILE TPB15
PREPARATION WORK FOR MAINTAINED LOAD TEST ON TPB18
TPB18- PLACING HYDRAULIC JACKS UNDER REACTION GIRDER
PILING WORK FOR MC’S TEST PILES ONGOING
FENCING AT SOUTH SIDE IN GOOD PROGRESS
PREPARATION OF AREA FOR CONSTRUCTION OF SITE BATCHING PLANT BY CPAC
04 March, 2015
02.03.15
GENERAL SITE VIEW
SITE SITUATION TODAY
PREPARATION WORK FOR MAINTAINED LOAD TEST ON PILE
TPB15
COUNTER WEIGHTS FOR TESTING OF PILE
TPB15
PREPARATION OF AREA FOR
TESTS ON TP11 & TP12
PILING WORK FOR MC’S TEST
PILES AT EAST SIDE
INSTALLATION OF SITE
TEMPORARY FACILITIES AT SOUTH-EAST
SITE PERIMETER FENCING AT SOUTH EAST SIDE COMPLETED
FENCING
AT SOUTH WEST SIDE IN PROGRESS
SCAFFOLDING DELIVERY
PREPARATION
OF AREA FOR CONSTRUCTION OF SITE BATCHING PLANT BY CPAC