13 May, 2015

13.05.15

THIRD SITE RIG IS MOBILISED - BAUER BG 25 

BORING BOILER ZONE C "LONG" PILE 

CASTING BOILER ZONE B PILES  

 BORING BOILER ZONE B PILE

CENTRAL BOILER PILING SURVEY CONTROL AREA 

 BORING BOILER ZONE B PILE

GENERAL SITE VIEW LOOKING WEST

11 May, 2015

11.05.15

GENERAL VIEW OF BOILER WORKS FROM THE EAST 

 INSTALLING PILE REBAR CAGE IN ZONE B

 CASTING PILE IN BOILER ZONE B

 CASTING BOILER PILE IN ZONE A

 BORING PILE IN BOILER ZONE A

ADDITIONAL TRIAL MIXES IN SITE BATCHING PLANT UNIT 1

09.05.15

BOILER PILE REBAR CAGE PREFABRICATION

 
BORING BOILER ZONE A PILES

 BORING BOILER ZONE A PILES 

 REBAR CAGE INSTALLATION ZONE A

CASTING BOILER ZONE A 1200MM DIA PILE 

 BORING BOILER ZONE B

 GENERAL VIEW FROM EAST LOOKING WEST OVER THE BOILER WORKS


08.05.15

 BORING BOILER ZONE B PILES

 BORING BOILER ZONE C PILES

 CASTING BOILER ZONE B PILE

PILING RIG RELOCATING IN BOILER ZONE B

 PILING RIG ZONE B

DELIVERING PREFABRICATED PILE REBAR CAGES 

CASTING ZONE B PILES 

 GENERAL VIEW OF BOILER PILING (EAST)


07 May, 2015

07.05.15

BAUER PILING COMMENCE PILING IN BOILER ZONE A
"21.05M LONG PILES" EAST (MILLS &  EAST SIDE OF FURNACE)

 PILING BALANCE OF WFGD ANCILLARY TANK FOUNDATIONS

INSTALLING CAGE ON BOILER ZONE A (P247)

BORING BOILER ZONE A PILES (P349)

 CASTING WFGD UNIT L39 PILES

CASTING LAST WFGD UNIT L39 PILE (L39-3)

TRIAL MIX RUNS ON SITE BATCHING PLANT UNIT 2 
(UNIT 1 OPERATIONAL & SUPPLYING SITE)

05 May, 2015

05.05.15

 PREFABRICATION OF B01 BOILER "LONG" 21.05M PILES 

 WFGD TANK PILES

STRIKING OF MLT RIG OFF B63 STH TP-B17 TO PREPARE FOR LATERAL TEST 

BAUER PILE REBAR CAGE PREFABRICATION  

SITE BATCHING PLANT UNIT 2 READY FOR TRIAL MIX 

SITE BATCHING PLANT UNIT 1 IS  OPERATIONAL
 - FIRST CONCRETE DELIVERED 2ND MAY 2015 

SITE BATCHING PLANT UNIT 1 IS  OPERATIONAL
 - FIRST CONCRETE DELIVERED 2ND MAY 2015  

NO WORKS BY CLIENT B/FILL CONTRACTOR DUE TO PUBLIC HOLIDAY

04.05.15

GENERAL SITE VIEW OF PILING OPERATION

BORED PILING ON LAST OF BOILER ZONE C 14.05M "SHORT" PILES

LIGNITE STRATA FOUND ON BOILER ZONE C PILES

CASTING PILES

INSTALLATION OF REBAR CAGES ON WFGD Lxx ANCILLARY TANK FOUNDATIONS

INSTALLATION OF SONIC LOGGER TUBES ON BOILER ZONE C SHORT PILE P164

LATERAL TEST ON B63 STH TP-B14

HEAVY RAIN AND WINDS FROM 1600HRS