11 September, 2015

10.09.15



WORKFRONT VIEW (WEST)


CURING AND STRIKING OF FORMWORK PROPS FOR PILECAP A1


WORKFRONT VIEW (SOUTH) 


PILEBREAKING FOR PILECAP ZONE C STARTED 


WORKFRONT VIEW (EAST)


DUCTBANK PILING (MC SCOPE) IN PROGRESS

10 September, 2015

09.09.15


START OF PILECAP A1 CONCRETE POUR


CONCRETING TEAM PREPARING AREA FOR CONCRETING


PILECAP A1 CONCRETING IN PROGRESS


INSTALLATION OF PILECAP A2 BOTTOM REINFORCEMENTS IN PROGRESS


INSTALLATION OF PILECAP A2 BOTTOM REINFORCEMENTS IN PROGRESS


INSTALLATION OF PILECAP A2 BOTTOM REINFORCEMENTS IN PROGRESS


PILECAP A1 CONCRETING APPROACHING COMPLETION.


09 September, 2015

08.09.15


PILECAP A4 PREPARATION PRIOR TO POUR


PILECAP A4 PREPARATION PRIOR TO POUR


PILECAP A4 FINALIZATION PRIOR TO POUR


START OF PILECAP A4 POUR


CONCRETING OF PILECAP A4 IN PROGRESS


CONCRETING OF PILECAP A4 IN PROGRESS

08 September, 2015

07.09.15




B01  - REINFORCEMENTS INSTALLATION AT ZONE A IN PROGRESS



B01 - PILECAP A1   


BORING PILE AT L24 AREA


REBAR PLACING AT L04 AREA


POURING PILE AT L43 AREA

04 September, 2015

03.09.15


B01 ZONE A PILECAP A4 FORMWORKS INSTALLATION IN PROGRESS


B01 ZONE A PILECAP A2 REINFORCEMENT INSTALLATION STARTED AND IN PROGRESS
  

B01 ZONE B (CENTER) PILE CUTTING IN PROGRESS


B01 ZONE B (NORTH) PILE CUTTING AND LEAN CONCRETE IN PROGRESS
  

L24 PILING IN PROGRESS

03 September, 2015

02.09.15


INSTALLATION OF ADDITIONAL STARTERS IN B01 ZONE A


MC SCOPE DUCTBANK PILING IN PROGRESS


TOP AND SIDE REINFORCEMENT INSTALLATION IN PILECAP A4
  

B01 ZONE A PILE CUTTING AND LEAN CONCRETE COMPLETED


ZONE B (NORTH) PILE CUTTING IN PROGRESS 


ZONE B (CENTER) PILE CUTTING IN PROGRESS 



B01 ZONE A PILECAP A4 FORMWORK INSTALLATION STARTED


B01 ZONE A PILECAP A4 FORMWORK INSTALLATION STARTED

01 September, 2015

31.08.15


B30 PILING IN PROGRESS


B01 PILECAP A4 BOTTOM REINFORCEMENTS COMPLETED.


B01 PILECAP A1 BOTTOM REINFORCEMENTS INSTALLATION IN PROGRESS. 


B01 ZONE B PILE CUTTING IN PROGRESS


B01 ZONE A FORMATION PILE CUTTING AT 98% COMPLETION