23 December, 2016

23.12.16

 B63 STH Perimetral wall
 B30 CEB View to North West
 B35 BEB View to West
 WFGD L04 Pumps Bldg View to East
 B10 ID Fan View to South
 WFGD Area View to West
WFGD L07 SRS Tank Foundation
 Underground Tanks Area View to West


20 December, 2016

20.12.16 Aerial Pictures Plant

B63 STH View to North East
B63 STH View to North East
B63 STH View to North
B63 STH Unloading bay at Lev+14.00

B63 STH View to North Lev +14.00m - ST LP upper outer casing installed
B63 STH Loading Bay
ST LP upper half outer casing installed
Condenser neck assembly/skidding in progress
Condenser modules getting ready for skidding
B63 STH View to South West
B30 CEB View to South West
B30 CEB View to North East
B35 BEB View to East
B35 BEB View to West

20.12.16 Aerial Pictures Boiler





20.12.16 Aerial ECS Area







20.12.16 Aerial pictures General view


 Overview to South East
 115kv SwichYard and SS Transformers
  Overview to South East
  Overview to East
  Overview to North East
 Laydown Areas 1,2 & 3
  Boiler & STH Overview to North
 Stack Artworks
GSUT Transformers
 G05 Demin Plant View to North
 Coal Conveyor Foundations View to North
 Cooling Tower and underground tanks View to South 
 Pipe Rack View to South East - BOP Piping installation in progress

17 December, 2016

17.12.16

 B35 Lev. 3.40
 B63 STH slabworks lev.0.00
  B63 STH slabworks lev.0.00
  B63 STH slabworks lev.0.00
 WFGD Booster fans
 WFGD Concrete tanks in progress
 ID Fan south motor erection
 WFGD L04 Pump bldg foundation
WFGD L07 Service bldg view to north