29 January, 2015

29.01.15




 BAUER BG24 RIG TEST DRIVING CASINGS & AUGERS
 BAUER BG24 RIG TEST DRIVING CASINGS & AUGERS
 BAUER BG24 RIG MODIFYING LOCKING CONNECTION ON CASING
 BAUER BG24 RIG MODIFYING LOCKING CONNECTION ON CASING
 NEXT CLIENT PLOT TO BE LEVELED AND RELEASED TO CONSORTIUM
  NEXT CLIENT PLOT TO BE LEVELED AND RELEASED TO CONSORTIUM
  NEXT CLIENT PLOT TO BE LEVELED AND RELEASED TO CONSORTIUM
 SITE HOARDING WORKS IN GOOD PROGRESS
SITE HOARDING MOCK UP SAMPLE APPROVED BY CLIENT
 AMC/CLIENT/NWRT/BAUER OFFERING FOR SUCCESSFUL PROJECT
 SITE SETTING OUT OF TEST PILES
REBAR PREFABRICATED FOR TEST PILES



28 January, 2015

28.01.15


  NWRT/BAUER Equipment on Standby
 Site Security Fencing in progress
 Site Fencing fabrication Works
 NWRT Equipment Deliveries
 NWRT Equipment & Site office 

27 January, 2015

27.01.15

 Clients Reclamation Contractor & Laydown
 Bauer Piling rigs & equipment
 EPC Temporary Offices
 Main Site Entrance
 Main Site Access Road
 Existing Filtration/Settlement ponds -potential use for Site dewatering & Screening
 Temporary Construction road though Reclaimed lay downs (SE)
 Bauer Offices & Equipment containers
 EPC Offices View East

26 January, 2015

26.01.15 - Test Pile Mobilisation

View North Across site 2 & Unit 4-7 Replacement Site

 Bauer Site Establishment

 Bauer Site Establishment

 Bauer Re-circulation & Pumping Equipment

Bauer BG25 Rig Ready to Bore

Nawarat Equipment on Site