16 June, 2015

15.06.15



EXCAVATION FOR 5 PDA PILECAPS COMPLETED


2ND 150T CRANE BOOM UP. 1ST 150T CRANE MOVED OUT OF L09 WORK AREA.


L05 ABSORBER TOWER PILING IN PROGRESS


L05 ABSORBER TOWER PILING IN PROGRESS


L09 EMERGENCY SCRUBBER DUMP PILING IN PROGRESS 


VIEW OF WORKFRONTS FROM THE SOUTH.


13 June, 2015

12.06.15


PILE CONCRETING IN ELECTROSTATIC PRECIPITATOR IN PROGRESS


PREPARATION OF SITE DRAINAGE (NORTH) IN PROGRESS 



ABSORBER TOWER PILE BORING IN PROGRESS


ASSEMBLY OF 2 X 150T CRANE IN PROGRESS. 1 NOS. CRANE BOOM-UP SUCCESSFULLY


EARTHWORKS IN EXTERNAL LAYDOWN AREA IN PROGRESS


12 June, 2015

11.06.15


VIEW FROM SOUTH OF BOILER AREA 


VIEW FROM EAST OF L05 ABSORBER TOWER


ROAD GRADING AND REBAR CAGE FABRICATION IN PROGRESS


STRUCTURAL STEEL ERECTION IN LAYDOWN AREA


ABSORBER TOWER PILE BORING IN PROGRESS 


ABSORBER TOWER PILE BORING IN PROGRESS



ELECTROSTATIC PRECIPITATOR PILE BORING AND CONCRETING IN PROGRESS



2 X 150T CRANE ASSEMBLY AND ERECTION IN PROGRESS. 



11 June, 2015

10.06.15



CONCRETING OF ELECTROSTATIC PRECIPITATOR PILES


PILING IN PROGRESS IN ABSORBER TOWER


PILE REINFORCEMENT CAGE INSTALLATION IN ABSORBER TOWER


REBAR FABRICATION YARD


ASSEMBLY OF 2 X 150 TONNES CRANE IN PROGRESS


ASSEMBLY OF 2 X 150 TONNES CRANE IN PROGRESS


PANORAMIC VIEW OF WORKFRONTS (ESP & ABSORBER TOWER)


PANORAMIC VIEW OF BOILER AREA

09 June, 2015

09.06.15

GENERAL VIEW OF SITE FROM SOUTH WEST

WEEKLY SAFETY INDUCTION

BORING OF ELECTROSTATIC PRECIPITATORS PILE

INSTALLING REBAR CAGE OF 
ELECTROSTATIC PRECIPITATORS PILE

CASTING OF ELECTROSTATIC PRECIPITATORS PILE

INSTALLING TREMIE PIPE FOR ABSORBER TOWER PILE

ASSEMBLY OF  NOS 2 x 150 TON CRAWLER CRANES
 IN PROGRESS 

08 June, 2015

08.06.15

   PIPING WORK AT ELECTROSTATIC PRECIPITATORS AREA    

BORING ELECTROSTATIC PRECIPITATORS PILE

INSTALLING REBAR CAGE ELECTROSTATIC PRECIPITATORS PILE

CASTING ELECTROSTATIC PRECIPITATORS PILE

REBAR PREFABRICATION YARD 

APS SITE OFFICE  PROGRESS

MC SITE OFFICE PROGRESS

EGAT SITE OFFICE PROGRESS

05 June, 2015

05.06.15

GENERAL SITE VIEW FROM SOUTH WEST

DELIVERY OF PREFABRICATED CAGES FOR BOILER PILES

INSTALLING REBAR CAGE BOILER ZONE A PILE

BORING BOILER ZONE A PILE

CASTING BOILER ZONE A PILE

SITE TEMPORARY DRAINAGE NETWORK
 IN PROGRESS

CLIENT RECLAMATION OF LAY DOWN AREA
 IN PROGRESS