29 April, 2015
28 April, 2015
27 April, 2015
27.04.15
BORING BOILER ZONE C "SHORT PILES"
CASTING BOILER ZONE C "SHORT PILES"
CASTING BOILER ZONE C "SHORT PILES"
DELIVERING REBAR CAGES TO BOILER ZONE C
BAUER PILE REBAR PREFABRICATION YARD
STRIPPING MLT RIG FROM STH TP-B14
COMPLETED WELFARE FACILITIES FOR WORKERS
PEDESTRIAN SEGREGATION FROM ROAD IN PROGRESS
CLIENT REMOVING TSF FROM FIRST PILE CEREMONY
APS SITE OFFICE PAD FOUNDATIONS IN PROGRESS
25 April, 2015
25.04.15 - CLIENT FIRST PILE CEREMONY
A SELECTION OF PHOTOS FROM THE DAYS EVENTS STARTING WITH PREPARATION THROUGH TO CONCLUSION.
NOTE THE "FIRST PILE" WAS BORED ON THE EVENING OF THE 24TH OF APRIL AND STABILISED USING POLYMER.
THE PILING TEAM THEN INSTALLED THE CAGE & TREMME PIPE ON THE MORNING OF THE CEREMONY IN PREPARATION FOR THE CASTING OF CONCRETE.
FOLLOWING SPEECHES AND PRESENTATIONS THE CASTING WAS STARTED BY THE SECTARY OF ENERGY BY REMOTE CONTROL TO THE CONCRETE WAGONS.
THIS WAS A WELL ATTENDED PRESS EVENT WHICH INCLUDED MANY DIGNITARIES, & VIP'S FROM THE CLIENT, CONSORTIUM, CONTRACTORS & LOCAL & NATIONAL ARENA