11 August, 2015

10.08.15


B30 PILING IN PROGRESS


B01 BOILER ZONE A SOUTH EXCAVATION STARTED.


FINALIZATION OF B01 BOILER ZONE C FIRST PHASE EXCAVATION 


B01 BOILER ZONE A (NORTH) EXCAVATION AND PILE CUTTING
  

TOWER CRANE MAST - STACKING IN PROGRESS

08 August, 2015

07.08.15


B30 PILING IN PROGRESS


B63 PILE CONCRETING IN  PROGRESS


TOWER CRANE (NORTH) FOUNDATION CAPPING COMPLETED.


TRIAL PILE BREAKING ON B35 PILE. 


MANUAL PILE BREAKING IN B01 BOILER ZONE A IN PROGRESS


MC CW PILING IN PROGRESS

07 August, 2015

06.08.15


START OF B30 PILING WORKS


B63 PILING IN PROGRESS


B63 PILE CONCRETING IN PROGRESS


B01 ZONE A PILE CUTTING IN PROGRESS (MANUAL LABOR WITH SLEDGEHAMMER, PICKS AND CHISELS)


IMPROVED SITE ACCESS AFTER POST RAIN CLEANUP. 

06 August, 2015

05.08.15



CW PILING IN PROGRESS (MC SCOPE)

+

POST RAIN CLEANUP ON SITE. 


B63 PILING IN PROGRESS

05 August, 2015

04.08.15



B63 PILING IN PROGRESS


B63 PILE CONCRETING


CURRENT B63 WORK FRONT


B01 BOILER ZONE A PILE HACKING IN PROGRESS

04 August, 2015

03.08.15


B63 PILING IN PROGRESS


B63 PILE CONCRETING


TOWER CRANE ERECTION COMPLETE. PENDING LOAD TEST.


COMPLETION OF B01 ZONE D PILES. B01 PILING IS OFFICIALLY COMPLETE


01 August, 2015

31.07.15


VIEW OF B63 PILING WORKFRONT (NORTH) 


PILE CONCRETING IN PROGRESS


ZONE A FINAL EXCAVATION IN PROGRESS


ZONE A FINAL EXCAVATION IN PROGRESS


B01 ZONE D PILING IN PROGRESS



TOWER CRANE CAT HEAD INSTALLATION IN PROGRESS


PILE CUTTING STARTED IN BOILER ZONE A