07.08.15
B30 PILING IN PROGRESS
B63 PILE CONCRETING IN PROGRESS
TOWER CRANE (NORTH) FOUNDATION CAPPING COMPLETED.
TRIAL PILE BREAKING ON B35 PILE.
MANUAL PILE BREAKING IN B01 BOILER ZONE A IN PROGRESS
MC CW PILING IN PROGRESS