11 September, 2015
10 September, 2015
09.09.15
START OF PILECAP A1 CONCRETE POUR
CONCRETING TEAM PREPARING AREA FOR CONCRETING
PILECAP A1 CONCRETING IN PROGRESS
INSTALLATION OF PILECAP A2 BOTTOM REINFORCEMENTS IN PROGRESS
INSTALLATION OF PILECAP A2 BOTTOM REINFORCEMENTS IN PROGRESS
INSTALLATION OF PILECAP A2 BOTTOM REINFORCEMENTS IN PROGRESS
PILECAP A1 CONCRETING APPROACHING COMPLETION.
09 September, 2015
08 September, 2015
07.09.15
B01 - REINFORCEMENTS
INSTALLATION AT ZONE A IN PROGRESS
B01 - PILECAP A1
BORING PILE AT L24 AREA
REBAR PLACING AT L04 AREA
POURING PILE AT L43 AREA
04 September, 2015
03 September, 2015
02.09.15
INSTALLATION OF ADDITIONAL STARTERS IN B01 ZONE A
MC SCOPE DUCTBANK PILING IN PROGRESS
TOP AND SIDE REINFORCEMENT INSTALLATION IN PILECAP A4
B01 ZONE A PILE CUTTING AND LEAN CONCRETE COMPLETED
ZONE B (NORTH) PILE CUTTING IN PROGRESS
ZONE B (CENTER) PILE CUTTING IN PROGRESS
B01 ZONE A PILECAP A4 FORMWORK INSTALLATION STARTED
B01 ZONE A PILECAP A4 FORMWORK INSTALLATION STARTED
01 September, 2015