01 September, 2015

31.08.15


B30 PILING IN PROGRESS


B01 PILECAP A4 BOTTOM REINFORCEMENTS COMPLETED.


B01 PILECAP A1 BOTTOM REINFORCEMENTS INSTALLATION IN PROGRESS. 


B01 ZONE B PILE CUTTING IN PROGRESS


B01 ZONE A FORMATION PILE CUTTING AT 98% COMPLETION