BOILER A 2 PILECAP TOP REBAR IN PROGRESS
BOTTOM REBAR FOR PILECAP B1 STARTED AND IN PROGRESS
PANORAMIC VIEW OF PILECAP A2 (NORTH AND SOUTH)
ZONE B AND ZONE C WORKFRONT
EXCAVATION IN ZONE C IN PROGRESS
L24 PILING IN PROGRESS
STG EXCAVATION IN PROGRESS