24 April, 2015

24.04.15

MLT TESTING RIG - STH TP-B17

MLT TEST RIG - STH TP-B14

    PREPARING TO CAST BOILER PILE

SETTING CASING ON BOILER PILE

PREPARATIONS FOR FIRST PILING CEREMONY

PREPARATIONS FOR FIRST PILING CEREMONY

TEMPORARY PROJECT SIGN BOARDS


22.04.15

 TRIAL MIXES START AT SITE BATCHING PLANT

 TRIAL MIXES START AT SITE BATCHING PLANT

EXTENT OF CLIENT BACK FILL PROGRESS 

EXTENT OF CLIENT BACK FILL PROGRESS  

EXTENT OF CLIENT BACK FILL PROGRESS 

21 April, 2015

21.04.15

DRY BORING BOILER ZONE C PILES THROUGH MUD STONE 

DRY BORING BOILER ZONE C PILES THROUGH MUD STONE  

DRY BORING BOILER ZONE C PILES THROUGH MUD STONE 

BOILER ZONE C PILE READY FOR CASTING

 CLIENT AREA PREPARATIONS FOR GROUND BREAKING CEREMONY

 CLIENT AREA PREPARATIONS FOR GROUND BREAKING CEREMONY

LAST MLT COMPRESSION TEST ON BOILER "LONG" PILES COMPLETE

20 April, 2015

20.04.15



BORING BOILER PILES IN ZONE C 
(EAST - SUPER HEATER & DUCT SUPPORTS)

                                                      BORING BOILER PILES IN ZONE C 
(EAST - SUPER HEATER & DUCT SUPPORTS)

COMPRESSION (MLT) TESTING OF BOILER "LONG" TP-B22

 STRIKING COMPRESSION (MLT) TEST RIG 
FROM BOILER "LONG"TP-B23 TO STH TP-B14

SITE BATCHING PLANT AWAITING FINAL POWER 
CONNECTION DUE 1800HRS 20T APRIL'15

                                     
CLIENT BACK FILL CONTRACTOR AT WORK ON LAY DOWN AREAS

CONTRACTORS 120T MOBILE CRANE DOWN FOR MAJOR REPAIR 

18 April, 2015

18.04.15 - START OF MMO PERMANENT WORKS - B01 BOILER PILING

BAUER PILING TEAM PREPARING PILING RIG FOR OPERATION 

PILING (No.158,157 & 185) LOCATION PREPARED ON 17.04.15

MOBILISATION OF RIG TO FIRST PILE No. 158

14.5M LONG 1.2M DIAMETER "SHORT" PILE REBAR CAGES PREFABRICATED 

SETTING THE CASING ON FIRST PILE

SETTING THE CASING ON FIRST PILE

 SETTING THE CASING ON FIRST PILE

SETTING AUGER ON FIRST PILE

BORING COMMENCES ON MMO PROJECT



17 April, 2015

17.04.15



COMPRESSION (MLT) TEST RIG UNDER FINAL PREPARATION ON TP-B22 (BOILER 'LONG' PILE) 

 COMPRESSION (MLT) TEST RIG UNDER FINAL PREPARATION ON TP-B22 (BOILER 'LONG' PILE)

SITE CRAWLER CRANES ON "SAFE STOP" FOR PUBLIC HOLIDAY 

BAUER PILING RIG READY TO START BOILER BORED PILES 

GENERAL SITE VIEW NORTH FROM BATCHING PLANT ACCESS ROAD 

BATCHING PLANT UNIT 1 - READY TO START ONCE POWER IS TERMINATED

                      BATCHING PLANT UNIT 1 - READY TO START ONCE POWER IS TERMINATED 

                      GENERAL SITE VIEW NORTH EAST FROM BATCHING PLANT ACCESS ROAD 

11th April 2015 to 16th April 2015 - Songkran - No Contractor activity