20 April, 2015

20.04.15



BORING BOILER PILES IN ZONE C 
(EAST - SUPER HEATER & DUCT SUPPORTS)

                                                      BORING BOILER PILES IN ZONE C 
(EAST - SUPER HEATER & DUCT SUPPORTS)

COMPRESSION (MLT) TESTING OF BOILER "LONG" TP-B22

 STRIKING COMPRESSION (MLT) TEST RIG 
FROM BOILER "LONG"TP-B23 TO STH TP-B14

SITE BATCHING PLANT AWAITING FINAL POWER 
CONNECTION DUE 1800HRS 20T APRIL'15

                                     
CLIENT BACK FILL CONTRACTOR AT WORK ON LAY DOWN AREAS

CONTRACTORS 120T MOBILE CRANE DOWN FOR MAJOR REPAIR 