30 April, 2015

30.04.15

 PILING COMMENCES ON WFGD L39 TANK FOUNDATION

SECOND BAUER BG25 RIG SET UP WITH DOUBLE CASING 
TOOL TO DRIVE 1200MM & 800MM WITH QUICK HITCH FOR CHANGING AUGERS 


BG24 RIG BORING BOILER ZONE C PILES 

BORING BOILER ZONE C PILES 

 DRY BORING BOILER ZONE C PILES 
                                                    
DELIVERY OF SITE PREFABRICATED REBAR CAGES FOR BOILER PILES 

APS SITE OFFICE FOOTINGS FOR GROUND BEAMS COMPLETED 
GROUND BEAM REBAR STARTED