GENERAL SITE VIEW OF PILING OPERATION
BORED PILING ON LAST OF BOILER ZONE C 14.05M "SHORT" PILES
LIGNITE STRATA FOUND ON BOILER ZONE C PILES
CASTING PILES
INSTALLATION OF REBAR CAGES ON WFGD Lxx ANCILLARY TANK FOUNDATIONS
INSTALLATION OF SONIC LOGGER TUBES ON BOILER ZONE C SHORT PILE P164
LATERAL TEST ON B63 STH TP-B14
HEAVY RAIN AND WINDS FROM 1600HRS