GENERAL SITE VIEW OF PILING OPERATION

BORED PILING ON LAST OF BOILER ZONE C 14.05M "SHORT" PILES

LIGNITE STRATA FOUND ON BOILER ZONE C PILES

CASTING PILES

INSTALLATION OF REBAR CAGES ON WFGD Lxx ANCILLARY TANK FOUNDATIONS

INSTALLATION OF SONIC LOGGER TUBES ON BOILER ZONE C SHORT PILE P164

LATERAL TEST ON B63 STH TP-B14

HEAVY RAIN AND WINDS FROM 1600HRS