07 May, 2015

07.05.15

BAUER PILING COMMENCE PILING IN BOILER ZONE A
"21.05M LONG PILES" EAST (MILLS &  EAST SIDE OF FURNACE)

 PILING BALANCE OF WFGD ANCILLARY TANK FOUNDATIONS

INSTALLING CAGE ON BOILER ZONE A (P247)

BORING BOILER ZONE A PILES (P349)

 CASTING WFGD UNIT L39 PILES

CASTING LAST WFGD UNIT L39 PILE (L39-3)

TRIAL MIX RUNS ON SITE BATCHING PLANT UNIT 2 
(UNIT 1 OPERATIONAL & SUPPLYING SITE)