BAUER PILING COMMENCE PILING IN BOILER ZONE A
"21.05M LONG PILES" EAST (MILLS & EAST SIDE OF FURNACE)
PILING BALANCE OF WFGD ANCILLARY TANK FOUNDATIONS
INSTALLING CAGE ON BOILER ZONE A (P247)
BORING BOILER ZONE A PILES (P349)
CASTING WFGD UNIT L39 PILES
CASTING LAST WFGD UNIT L39 PILE (L39-3)
TRIAL MIX RUNS ON SITE BATCHING PLANT UNIT 2
(UNIT 1 OPERATIONAL & SUPPLYING SITE)