PREFABRICATION OF B01 BOILER "LONG" 21.05M PILES
WFGD TANK PILES
STRIKING OF MLT RIG OFF B63 STH TP-B17 TO PREPARE FOR LATERAL TEST
BAUER PILE REBAR CAGE PREFABRICATION
SITE BATCHING PLANT UNIT 2 READY FOR TRIAL MIX
SITE BATCHING PLANT UNIT 1 IS OPERATIONAL
- FIRST CONCRETE DELIVERED 2ND MAY 2015
SITE BATCHING PLANT UNIT 1 IS OPERATIONAL
- FIRST CONCRETE DELIVERED 2ND MAY 2015
NO WORKS BY CLIENT B/FILL CONTRACTOR DUE TO PUBLIC HOLIDAY