GENERAL VIEW BOILER PILING WORKS TO WEST
BORING IN BOILER ZONE A
INSTALLING PILE REBAR CAGE ZONE B
CASTING PILE BOILER ZONE A
BOILER PILE REBAR CAGE FABRICATION
REMOVAL OF EXCAVATED MATERIAL FROM SITE
APS SITE OFFICE - FOUNDATION WORK IN PROGRES
EGAT SITE OFFICE - INSTALLATION OF FIRST COLUMN
BATCHING PLANT MMO-01 IN OPERATION
BATCHING PLANT MMO-02 IN OPERATION