08 April, 2015

08.04.15

 COMPRESSION TESTING (MLT) CONTINUES ON BOILER "LONG" TP-B23
MAX LOAD 450.05TONS

RELOCATION OF MLT RIG TO BOILER "LONG"TP-B22 - IN PROGRESS

COMPRESSION TESTING (MLT) OF ECS/Lxx TP-B20 

PREPARATION OF CEREMONIAL FIRST PILE AREA

CLEARING COMPLETED TEST PILE AREAS

EHS MANAGERS SITE WALKDOWN