18 July, 2015

17.05.17


VIEW OF WORK FRONT FROM THE WEST


REBAR ASSEMBLY FOR TOWER CRANE PILECAP (WEST)


B63 PILING IN PROGRESS


B63 PILE REBAR CAGE INSTALLATION 


B63 PILE CONCRETING

17 July, 2015

16.07.15


COMPLETED DEWATERING PIT AND PILE CUTTING COMPLETE FOR TOWER CRANE FOUNDATION.


PANORAMIC VIEW OF B63 WORK FRONT


PILE CONCRETING IN PROGRESS IN B63


PILE BORING IN PROGRESS


EXCAVATION IN B01 ZONE B IN PROGRESS


PANORAMIC VIEW FROM SOUTHEAST.

16 July, 2015

15.07.15


TOWER CRANE FOUNDATION (WEST) PILE EXCAVATION


RELOCATION AND RE-INSTALLATION OF DEWATERING PIT IN B63


B63 PILING IN PROGRESS


PILE REBAR CAGE INSTALLATION IN B63


EXCAVATION IN B01 ZONE B IN PROGRESS

14 July, 2015

14.07.15


VIEW OF B63 WORK FRONT FROM THE SOUTHEAST


EXCAVATION OF ZONE B IN PROGRESS


B63 PILE BORING IN PROGRESS


B63 PILE REBAR CAGE INSTALLATION


B63 PILE CONCRETING IN PROGRESS

13.07.15


IMPROVED B63 ACCESS


REBAR CAGE INSTALLATION FOR B63 PILE


INSTALLATION OF PVC PIPES ONTO PILE STARTER BARS


RESUMPTION OF ZONE B EXCAVATION


PANORAMIC VIEW OF WORKFRONT FROM THE SOUTH


REBAR CAGES FABRICATION IN PARTNER'S SUBCONTRACTOR YARD


APS OFFICE - PERIMETER WALL PLASTERING COMPLETE


EARTHWORKS ON EXTERNAL LAYDOWN IN PROGRESS

12 July, 2015

11.07.15




MODIFICATION ON ACCESS STEEL PLATES TO IMPROVE ACCESS TRACTION


B63 PILING AND RESIDUAL EXCAVATION TO B63 AREA IN PROGRESS


ACCESS IMPROVEMENT IN PROGRESS  


B63 PILE CONCRETING IN PROGRESS


INSTALLATION OF PVC PIPES ON STARTER BARS OF PILE CAGES IN PROGRESS


PANORAMIC VIEW OF B63 WORKFRONT FROM THE SOUTH

11 July, 2015

10.07.15


B63 PILING IN PROGRESS


REBAR CAGE INSTALLATION FOR B63 PILES.
  

PREPARATION OF REBAR CAGES FOR B63 PILES PRIOR TO CONCRETING


BOILER EXCAVATION ON HOLD DUE TO ACCESS RECTIFICATION


PANORAMIC VIEW FROM WEST OF B63