13.07.15


IMPROVED B63 ACCESS


REBAR CAGE INSTALLATION FOR B63 PILE


INSTALLATION OF PVC PIPES ONTO PILE STARTER BARS


RESUMPTION OF ZONE B EXCAVATION


PANORAMIC VIEW OF WORKFRONT FROM THE SOUTH


REBAR CAGES FABRICATION IN PARTNER'S SUBCONTRACTOR YARD


APS OFFICE - PERIMETER WALL PLASTERING COMPLETE


EARTHWORKS ON EXTERNAL LAYDOWN IN PROGRESS