MMO
1x600MW ULTRA SUPER CRITICAL LIGNITE POWER PLANT
09 July, 2015
08.07.15
B63 EXCAVATED AREA
MOBILIZATION OF RIG FROM CW AREA TO B63 AREA FOR CASING DRIVING.
BOILER ZONE B EXCAVATION IN PROGRESS
DEWATERING ARRANGEMENT IN EXCAVATED AREAS OF B63 AND B01 ZONE A
B63 PILING REBAR CAGE FABRICATION IN PROGRESS