1x600MW ULTRA SUPER CRITICAL LIGNITE POWER PLANT
10 July, 2015
09.07.15
COMMENCEMENT OF PILING IN B63 TURBINE HALL
SLIPPERY ACCESS INTO B63 WORK FRONT. PARTNER IS TAKING STEPS TO IMPROVE ACCESS.
VIEW OF ADJACENT AREA OF BOILER ZONE A
CONCRETING OF B63 PILE
FABRICATION OF REBAR CAGES IN PROGRESS FOR B63