17 October, 2015
16 October, 2015
15.10.15
PILECAP C12 PRE-CONCRETING INSPECTION
PILECAP B3 FORMWORKS FINALIZATION
EXPOSED FINAL 2 PILES IN ZONE B
EXCAVATION FOR CW LINE. (MC SCOPE)
CONCRETING OF PILECAP C12
PRE-CONCRETING INSPECTION FOR EMBEDDED ITEMS (PEDESTALS ZONE A)
PRE-CONCRETING INSPECTION FOR EMBEDDED ITEMS (PEDESTALS ZONE A)
CURING OF PILECAP C12
15 October, 2015
14 October, 2015
11 October, 2015
10 October, 2015
09 October, 2015
08.10.15
PRE CONCRETING INSPECTION FOR ANCHOR BOLTS AND PEDESTALS.
B3-3 CONCRETING IN PROGRESS
B3-3 CONCRETING IN PROGRESS
REBAR AND FORMWORKS INSTALLATION IN ZONE B
ZONE C PILE HACKING NEARING COMPLETION
EXCAVATION AND PILE BREAKING IN CW AREA IN PROGRESS
PEDESTAL CONCRETING COMPLETED AND VERIFICATION SURVEY.