17 October, 2015

16.10.15


CW PIPE SADDLES REBAR INSTALLATION IN PROGRESS


PRE-CONCRETING INSPECTION FOR EMBEDDED ITEMS (PEDESTALS ZONE A)


PRE-CONCRETING INSPECTION FOR EMBEDDED ITEMS (PEDESTALS ZONE A)


PILECAP B3 CONCRETING IN PROGRESS


ZONE A PEDESTAL WORKS IN PROGRESS


B64 PILING IN PROGRESS

16 October, 2015

15.10.15


PILECAP C12 PRE-CONCRETING INSPECTION


PILECAP B3 FORMWORKS FINALIZATION


EXPOSED FINAL 2 PILES IN ZONE B


EXCAVATION FOR CW LINE. (MC SCOPE)


CONCRETING OF PILECAP C12


PRE-CONCRETING INSPECTION FOR EMBEDDED ITEMS (PEDESTALS ZONE A)


PRE-CONCRETING INSPECTION FOR EMBEDDED ITEMS (PEDESTALS ZONE A)


CURING OF PILECAP C12

15 October, 2015

14.10.15


PRE-CONCRETING INSPECTION FOR EMBEDDED ITEMS (PEDESTALS ZONE A)


PRE-CONCRETING INSPECTION FOR EMBEDDED ITEMS (PEDESTALS ZONE A)


B64 PILING IN PROGRESS

14 October, 2015

13.10.15


PILECAP B3 REBAR INSTALLATION IN PROGRESS


PILECAP C12 REINFORCEMENT INSTALLATION IN PROGRESS


ZONE A PEDESTAL WORKS IN PROGRESS


PILECAP B3 FORMWORK INSTALLATION IN PROGRESS



PILECAP C12 FORMWORKS IN PROGRESS

11 October, 2015

10.10.15


PEDESTAL REBAR INSTALLATION IN PROGRESS (B01 ZONE A)
  

B01 ZONE B SOUTH REBAR INSTALLATION IN  PROGRESS


PREPARATION FOR ZONE C REBAR WORKS


B64 PILING IN PROGRESS


10 October, 2015

09.10.15


B64 PILING IN PROGRESS


B64 PILING IN PROGRESS


PEDESTAL CURING IN PROGRESS


09 October, 2015

08.10.15






PRE CONCRETING INSPECTION FOR ANCHOR BOLTS AND PEDESTALS. 


B3-3 CONCRETING IN PROGRESS


B3-3 CONCRETING IN PROGRESS


REBAR AND FORMWORKS INSTALLATION IN ZONE B


ZONE C PILE HACKING NEARING COMPLETION


EXCAVATION AND PILE BREAKING IN CW AREA IN PROGRESS


PEDESTAL CONCRETING COMPLETED AND VERIFICATION SURVEY.