24 June, 2015
23.06.15
EXCAVATION AT BOILER ZONE A (+ TURBINE HALL) STARTED
EXCAVATION AT BOILER ZONE A (+ TURBINE HALL) STARTED
2ND EXCAVATOR FOR BOILER EXCAVATION IN PROGRESS
PDA PILES PREPARATION IN PROGRESS (CONTINUED)
B17 PILES IN PROGRESS