30 September, 2015

29.09.15


FINAL POSITIONAL SURVEY IN PROGRESS


FORMWORKS ADJUSTMENT AFTER SURVEY IN PROGRESS


KICKER SETTING OUT AND REBAR CHECK IN PROGRESS


KICKER SETTING OUT AND REBAR CHECK IN PROGRESS


PILECAP B2 BOTTOM MATT REBAR INSTALLATION IN PROGRESS



PILECAP A2 CURING IN PROGRESS 


WORKFRONT ZONE B (SOUTH) 

29 September, 2015

28.09.15


STARTER REBAR AND TEMPORARY ROOF INSTALLATION IN PROGRESS


COMPLETED PILECAP A2 (PARTIAL) CURING IN PROGRESS



WORKFRONT ZONE B AND ZONE C


BOTTOM MATT REBAR INSTALLATION IN PROGRESS

27 September, 2015

26.09.15


PILECAP A2 (NORTH) FINALIZATION


FINAL DIMENSIONAL/POSITIONAL SURVEY 


FIRST POUR STARTS 0825 HOURS


PILECAP A2 (NORTH) CONCRETING IN PROGRESS


PILECAP A2 (NORTH) CONCRETING IN PROGRESS


PILECAP B1-1 STARTER BAR INSTALLATION IN PROGRESS


PILECAP B2 BOTTOM MATT REBAR INSTALLATION IN PROGRESS


26 September, 2015

25.09.15


PILECAP A2 (NORTH)-WORKS IN PROGRESS 


PILECAP B1-1 FORMWORKS AND HY-RIB INSTALLATION IN PROGRESS


ZONE C PILE HACKING IN PROGRESS 


ZONE C PILE HACKING IN PROGRESS




25 September, 2015

24.09.15


FINAL PREPARATIONS PRIOR TO CASTING



POSITIONING OF CONCRETEPUMPS TO CONCRETING AREAS


FIRST CONCRETE POURED IN PILECAP A2 (SOUTH) 




CONCRETING ON PILECAP A2 (SOUTH) IN PROGRESS


FINISHING WORKS ON TOC


FINISHING WORKS ON TOC


PILE HACKING IN ZONE C IN PROGRESS


PILECAP B1 - WORKS IN PROGRESS



PILECAP B1 - WORKS IN PROGRESS


24 September, 2015

23.09.15


PILECAP A2 (SOUTH) TEMPORARY ACCESS AND FORMWORKS ERECTION IN PROGRESS


PILECAP B1 REBAR INSTALLATION IN PROGRESS 


PILECAP B1 REBAR INSTALLATION IN PROGRESS 


PILECAP A2 (SOUTH) TEMPORARY ACCESS AND FORMWORKS ERECTION IN PROGRESS


KICKER INSTALLATION NEAR PEDESTAL AREAS. POSITIONAL SURVEY COMMENCED.

22 September, 2015

21.09.15


PILECAP A2 AND B1 PANORAMIC VIEW


PILECAP A2 (SOUTH) PEDESTAL REBAR INSTALLATION IN PROGRESS


FORMWORKS FOR PILECAP A2 IN PROGRESS


L24 PILING IN PROGRESS


PILECAP A2 (SOUTH)


PILECAP B1

20 September, 2015

19.09.15


STG HALL EXCAVATION IN PROGRESS
  

PILECAP A2 REBAR INSTALLATION IN PROGRESS


PILECAP B1 REBAR INSTALLATION IN PROGRESS



B01 ZONE A


B01 ZONE B

18 September, 2015

17.09.15


BOILER A 2 PILECAP TOP REBAR IN PROGRESS


BOTTOM REBAR FOR PILECAP B1 STARTED AND IN PROGRESS


PANORAMIC VIEW OF PILECAP A2 (NORTH AND SOUTH)


ZONE B AND ZONE C WORKFRONT


EXCAVATION IN ZONE C IN PROGRESS


L24 PILING IN PROGRESS


STG EXCAVATION IN PROGRESS