03 March, 2017

03-03-17

B30 - CEB Electrical Building South side view
B33 - CEB Electrical Building - Main Control Room view
B30 - CEB Electrical Building Roof structure view
B30 - CEB Electrical Building - F.F water pipes erection
B30 - CEB Electrical Building Bus bars supports erection
Electrical cable pulling activities
Electrical cable pulling activities
B30 - CEB Electrical Building cable pulling activities
F05 - Switchyard 115 kV Supports / Gantry's  erection
F05 - Switchyard 230 kV Supports / Gantry's  erection
B68 - GSUT Transformer Area view from ECB
B35 - BEB Electrical Building construction
B35 - BEB Electrical Building construction
B35 - BEB Electrical Building construction
63 - STH Roof view from Boiler
63 - STH Baby turbines construction
B95 -  Condensate Polishing Plant construction
B63 - STH  B42 BFWP preparation for erection
B63 - STH  FW Tank Area platform & Piping erection
B01 - Boiler West side view
B01 - Boiler vent piping and silencers erection - Exhaust vent
B01 - Boiler Roof Area view
B01 - Boiler coal piping erection
B01 - Boiler coal feeder system erection
B01 - Boiler pressure parts erection
B01 - Boiler pressure parts erection
B01 - Boiler piping erection
B37 - ESP South - West view
B37 - ESP & Pipe Rack North - West view
L06 - WFGD Electrical Building construction
L06 - WFGD Electrical Building construction
L07 - WFGD Service Building construction
L07 - WFGD Service Building construction
WFGD Pipe trench construction