05 August, 2017

05-08-17

Plant view from West side
F05 - 230 kV Swyr. + B68 - Transformer area view from South-West side
F05 - 230 kV Swyr. area view from South side
F05 - 230 kV Swyr. area view from B30 - CEB
F05 - 115 kV Swyr. area view from B30 - CEB
B68 - Transformer area view from South-West side
B68 - Transformer area Bus Ducts erection activities
B68 - Transformer area Bus Ducts erection activities
B68 - Transformer area Bus Ducts erection activities
B68 - Transformer area Bus Ducts erection activities
B68 - Transformer area Bus Bars erection activities
B68 - Transformer area view from South side
B30 - CEB view from South side
B30 - CEB view from B63 - STH
B30 - CEB Raised floor installation activities
B33 - CEB Main Control Room view
B30 - CEB External view from North-East side
B30 - CEB Toilets Civil works activities
B30 - CEB Toilets Civil works activities
B63 - STH view from South-East side
B63 - STH North side wall Cladding erection activities
B63 - STH Fire Fighting System erection activities
B63 - STH view from West side
B63 - STH Cable trays erection activities
B64 - Power Train view from West side
B64 - Power Train view from South-West side
B63 - STH Elev +14.00 m view from South-West side
B64 - Generator view from South side
B63 - STH Elev +14.00 m view from South-East side
B64 - Power Train Piping erection activities
B64 - Power Train Shaft Alignment activities
B64 - Power Train Shaft Alignment activities
B64 - Power Train Shaft Alignment activities
B64 - BFWPT erection activities
B64 - BFWPT erection activities
B64 - BFWPT erection activities
B64 - BFWPT erection activities
B64 - BFWPT erection activities
B64 - BFWPT erection activities
B63 - STH Elev +14.00 m view from West side
B63 - STH Elev +14.00 m view from East side
B63 - STH Elev +14.00 m Piping erection activities
External Fire Fighting Main Ring installation activities
B95 - CPP Condensate Polishing Plant view from West side
B95 - CPP Condensate Polishing Plant view from South side
B95 - CPP Condensate Polishing Plant view from South-West side
B01 - Boiler & B63 - STH view from North-East side
B01 - Boiler view from North side
B01 - Boiler view from North-East side
B01 - Boiler view from South-East side
B01 - Boiler view from South side
B01 - Boiler Coal System view from North side
B01 - Boiler South FD Fan & PA Fan view
B01 - Boiler Pulverizer Area view from North-West side
B01 - Boiler Pulverizer Area Piping erection activities
B35 - Boiler Electrical Bldg.view from West side
B35 - Boiler Electrical Bldg.view from East side

B35 - Boiler Electrical Bldg. external Cable trays erection activities
B07 - ESP view from North-West Side
B07 - ESP view from North-East Side
B01 - Boiler & B07 - ESP view from North-East Side
B07 - ESP view from South-East Side
B07 - ESP view from South Side
B07 - ESP view from South-West Side
B17 - Flue Gas ducts Civil works activities view from South Side
B10 - ID Fan North side view
B10 - ID Fan South side view
L04 - WFGD Pump Bldg. view from North-East side
L04 - WFGD Pump Bldg.GRP Piping erection activities
L05 - WFGD Absorber - Reactor view from East side.
WFGD Area view from North side.
L38 - WFGD Local Gypsum Slurry Tank view from East side.
L06 - WFGD Electrical Bldg. view from North-West side.
L06 - WFGD Electrical Bldg. view from South side.
L06 - WFGD Electrical Bldg. F.F. System erection activities.
L07 - WFGD Service Bldg. view from South side.
L07 - WFGD Service Bldg. view from South-East side.
L07 - WFGD Service Bldg. Civil works construction activities
L07 - WFGD Service Bldg. Reclaim Water tank erection activities.
L09 - WFGD Auxiliary Storage tank view from North side.
L09 - WFGD Auxiliary Storage tank view from East side.
L09 - WFGD Auxiliary Storage tank view from South side.
L35 - WFGD Washing tank view from East side.
L37 - WFGD Purge tank erection activities.
WFGD Waste Water Treatment Bldg. Civil works construction activities
L10 - WFGD Booster Fans Bldg. view from South side.
L24 - WFGD Fue gas Ducts view from South side.
L24 - WFGD Fue gas Ducts view from South side.
L24 - WFGD Fue gas Ducts Prea-ssembly activities.
E06 - CW Treatment Bldg. view from South-West side
E06 - CW Treatment Bldg. Equipment erection activities
E06 - CW Treatment Bldg. Services erection activities
E07 - CW Electrical Bldg. view from North-West side
E04 - Cooling Tower view from North side
E04 - Cooling Tower cable pulling activities
E04 - Cooling Tower view from South side
E12 - Cooling Tower Pumping Station view from North-East side
E12 - Cooling Tower Pumping Station view from South-East side
G42 - Fire Fighting Pump Station view from South side
G42 - Fire Fighting Pump Station view from East side
G10 - Emergency Diesel Generator view from B30 - CEB
C01 - Fuel oil Tank view from B30 - CEB
C01 - Fuel oil Tank Civil works Construction activities
C03 - Fuel oil Pump Station Civil works Construction activities
C07 - Coal Transfer Tower erection activities
C06 - Coal Conveyor erection activities
C06 - Coal Conveyor erection activities
C06 - Coal Conveyor erection activities
C06 - Coal Conveyor erection activities
C06 - Coal Conveyor erection activities
C06 - Coal Handling Electrical Bldg. view from South-East Side
D08 - Ash Sub distribution Bldg. view from South-West side
D08 - Ash Sub distribution Bldg. view from South-East side
D20 - Fly Ash Compressor Bldg. view from South-West side
D20 - Fly Ash Compressor Bldg. view from South-East side
G21 - NH3 Storage Bldg. view from South-East side
B89 - Compressed Gas Storage House view from South-East side
B89 - Compressed Gas Storage House view from South side

No comments: