08 August, 2017

08-08-17

B33 - CEB Main Control Room Raised floor installation activities
B33 - CEB Main Control Room Raised floor installation activities
B33 - CEB Main Control Room False ceiling installation activities
B33 - CEB Temporary Control Room for Back feed energization
B33 - CEB Temporary Control Room for Back feed energization
B63 - STH North side wall cladding view
B63 - STH BFWPT Lube oil room civil completion activities
B63 - STH BFWPT Lube oil room civil completion activities
B01 - Boiler Pulverizer Area view from South-West side
B01 - Boiler Ground slab civil works construction activities
 
B01 - Boiler Ground slab civil works construction activities
B01 - Boiler Ground slab civil works construction activities
B01 - Boiler Pressure parts erection activities
B01 - Boiler Pressure parts erection activities
B01 - Boiler Pressure parts erection activities
B01 - Boiler Pressure piping erection activities
B01 - Boiler Pressure piping erection activities
B01 - Boiler Pressure piping erection activities
B01 - Boiler Ducts erection activities
B01 - Boiler Ducts erection activities (Expansion Joints)
B01 - Boiler Ducts erection activities
B01 - Boiler Ducts erection activities (Expansion Joints)
B01 - Boiler piping erection activities (ammonia injection)
B01 - Boiler piping erection activities (ammonia injection)
B01 - Boiler piping erection activities (ammonia injection)
B01 - Boiler piping erection activities (ammonia injection)
B01 - Boiler piping erection activities (ammonia injection)
B01 - Boiler piping erection activities (ammonia injection)
B01 - Boiler piping erection activities (ammonia injection)
B01 - Boiler piping erection activities(F.F. water sys)
South Laydown yard view from B01 - Boiler
South Laydown yard view from B01 - Boiler
ESP and WFGD Area  view from B01 - Boiler
ESP and WFGD Area  view from B01 - Boiler
ESP and WFGD Area  view from B01 - Boiler
ESP and WFGD Area  view from B01 - Boiler
WFGD Area  view from B01 - Boiler
B17 - Flue Gas ducts Supports Civil works construction activities
L06 - WFGD Electrical Bldg. view from North-West side
L06 - WFGD Electrical Bldg. Roof structure erection activities
L06 - WFGD Electrical Bldg. civil works construction activities
L06 - WFGD Electrical Bldg. Roof structure erection activities
L06 - WFGD Electrical Bldg. Roof structure erection activities
L07 - WFGD Service Bldg. view from South-East side
L07 - WFGD Service Bldg.Steel structure erection activities
L07 - WFGD Service Bldg. civil works construction activities
L07 - WFGD Service Bldg. civil works construction activities
L07 - WFGD Service Bldg. civil works construction activities
L07 - WFGD Service Bldg. civil works construction activities
WFGD Waste water treatment Bldg. Steel structure erection activities
WFGD Waste water treatment Bldg. Steel structure erection activities
WFGD Waste water treatment Bldg. Steel structure erection activities