17 May, 2018

17-05-18

B63 - STH view from South-East side
B63 - STH West side wall cladding erection activities
B63 - STH East side wall cladding erection activities
B63 - STH turbine feedwater tank area view from East side
B64 - ST turbine area view from North-East side
B64 - Generator hydrogen filling activities
B01 - Boiler Ammonia pipe area view
B10 - Boiler North side ID Fan A area view
B06 - Boiler Coal Bunker tripper deck area conveyor belt testing activities
B07 - ESP view from B01 - Boiler
B07 - ESP #1 area view from B01 - Boiler
B07 - ESP #2 area view from B01 - Boiler
B07 - ESP 2 outlet duct towards B10 - ID Fan B duct insulation activities
B89 - Compressed Gas Storage House H2 tanks view
WFGD view from South-West side
L09 - WFGD Auxiliary Storage Tank area view from South side
L24 - WFGD Ducts view from South-East side
G60 - Chemical Bulk Storage Bldg. area view from B01 - Boiler
G60 - Chemical Bulk Storage Bldg. civil work activities
D01 - Fly Ash Silo Storage Tank view from B01 - Boiler
D23 - Ash Receiving Station and D30 - Ash Loading Station view from B01 - Boiler
C06 - Coal Conveyors and H03 - Piperack view from B63 - STH
C07 - Transfer Tower #4 area view from B01 - Boiler
L15 - Gypsum Transfer Tower view from North-West side
L15 - Gypsum Transfer Tower view from East side
Plant South side of STH area road work activities
Plant South side of Boiler area road work activities
Plant South side of ESP area road work activities
Plant South side of WFGD area road work activities
Plant East side of Fly Ash Compressor Bldg. area road work activities
Plant North side of WFGD area road work activities
Plant North side of Lignite Sub-Distribution Bldg. area drainage work activities
Plant East side of WFGD area road work activities
Plant West side of Firefighting Pump station area road work activities