09 April, 2015

09.03.15




MLT TESTING OF TP-B23 CONTINUES 

ASSEMBLY OF MLT RIG ON TP-B22 

                                                   ASSEMBLY OF MLT RIG ON TP-B22  

                                                   ASSEMBLY OF MLT RIG ON TP-B22 

 B01 BOILER "SHORT" REBAR CAGE FABRICATION STARTED 

BAUER RE-MOBILISE TO TEST EQUIPMENT 
                                                   PENDING BOILER PILE RFC RELEASE

INSTALLATION OF TSF 

                                            INSTALLATION OF CLIENT CEREMONIAL AREA







08 April, 2015

08.04.15

 COMPRESSION TESTING (MLT) CONTINUES ON BOILER "LONG" TP-B23
MAX LOAD 450.05TONS

RELOCATION OF MLT RIG TO BOILER "LONG"TP-B22 - IN PROGRESS

COMPRESSION TESTING (MLT) OF ECS/Lxx TP-B20 

PREPARATION OF CEREMONIAL FIRST PILE AREA

CLEARING COMPLETED TEST PILE AREAS

EHS MANAGERS SITE WALKDOWN

07.04.15

COMPRESSION TEST (MLT) STARTED ON BOILER "LONG" TP-B23 

 COMPRESSION TEST (MLT) STARTED ON BOILER "LONG" TP-B23 

RELOCATION OF MLT TEST RIG TO BOILER "LONG" TP-B22 
FROM CHIMNEY TP-11 (MC) 

RELOCATION OF MLT TEST RIG TO BOILER "LONG" TP-B22 
FROM CHIMNEY TP-11 (MC) 

 ASSEMBLY OF MLT TEST RIG ON ECS/Lxx TP-B20

GENERAL SITE VIEW SOUTH

06 April, 2015

06.04.15




 ERECTION OF COMPRESSION TESTING RIG (MLT) ON TP-B23 (BOILER LONG)

ERECTION OF COMPRESSION TESTING RIG (MLT) ON TP-B23 (BOILER LONG) 

TP-B22 (BOILER LONG) - READY FOR ERECTION OF COMPRESSION TESTING RIG (MLT)

 SITE ACCESS ROADS IN PROGRESS TO FIRST PILE CEREMONIAL AREA

GENERAL SITE VIEW TO THE SOUTH EAST

03.04.15

 BATCHING PLANT READY FOR OPERATION


START OF EXCAVATION ON EPC OFFICE COMPLEX 

TSF - CONSTRUCTION OF VEHICLE WASHING STATION & WATER RECYCLE 

 LATERAL TEST ON TP-08 (WFGD)

COMPRESSION TESTING (MLT) TP-11 (MC) 

 FINAL PREPARATION OF TP-B23 (BOILER LONG) FOR TESTING RIG

COMPRESSION TESTING (MLT) OF TP-B11 (CHIMNEY MC) 
- RIG TO MOVE TO TP-B22 BOILER BY 7th APR'15


02 April, 2015

02.04.15

SITE BATCHING PLANT UNIT 1 

BALANCE OF SITE PERIMETER FENCING (SOUTH BOUNDARY) 

CLIENT PREPARING ACCESS FOR 1ST PILE CEREMONY 

FIRST FOOTINGS FOR EPC OFFICE 

LATERAL LOAD TESTING ON TP-B05 

TENSILE TESTING TP-B24

01 April, 2015

01.04.15

 GENERAL SITE VIEW WEST

GENERAL SITE VIEW SOUTH WEST

DYNAMIC TESTING TO TP-B23 (B01 NEW) 

GENERAL PREPARATION WORKS FOR TEST PILES 

(MLT) COMPRESSION TESTING OF TP-B12 COMPLETE