14 November, 2016

14.11.16 Aerials

 Overview to South East
 Overview to North East
Boiler View to North West 
Boiler View to West - Air Preheaters 
Boiler view to West 
Boiler PA & FD Fan North 
Boiler Pulverizer View to South 
 B63 STH View to North East
 B63 STH View to South
B63 STH View to South Lev.+14.00 
B63 STH View to South Lev.+6.00  
 B95 Condensate Polishing plant
 B30 CEB View to North
  B30 CEB View to South
B35 BEB View to East 
B35 BEB Top View
ESP & WFGD Area View to South West 
ESP & WFGD Area View to South
 ESP Steel Structure  & ID Fan Foundations Top View
WFGD  & ID Fan Foundations View to East
Laydown Area 1,2 & 3  East Part View to South - ESP Prefab zone  
Laydown Area 1,2 & 3  Central Part View to South - Boiler Prefab zone 
 Laydown Area 1,2 & 3  West Part View to South - Boiler Prefab zone 
Laydown  Area 7 View to East
Cooling Tower & Underground Storage Tanks View to South 
H03 - Pipe rack View to East 
H03 - Pipe rack View to East 

09 November, 2016

09.11.16

 Boiler Overview to North West
  Site Overview to South West
 Boiler PA Fan installation
 Boiler installation of Steel for PA Fan North
Boiler Pressure Part Furnace Hanging elements 
Boiler View of Airheaters from Furnace opening 
 B64 STH Lev.0.00 View to South
B64 STH GL 3-4 View to East 
B64 STH GL 4-5 View to East  
B64 STH -  B24 LP Heaters rail
 B64 STG Condenser area getting ready for skidding 
HP1 and HP2 Heaters
 B95 Polishing plant underground works
 B30 CEB Dry Transformers installation
 B35 BEB ground beams backfilling View to West
B35 BEB View to West 
 B68 UAT Transformer Foundation
B68 GSUT Foundations View to East 
 WFGD Area Overview to North West
 WFGD Absorber Floor Plate grid support steel installaition 
WFGD L07  Service Bldg View to north
WFGD L04 Pumps Bldg ground beams & backfill in progress 
E06 CW Blddg Slab poured
 B17 FGD Outlet View to South  
 Stack borosilicate

07 November, 2016

07.11.16

 Site Overview to South West
 Boiler Furnace opening View to North 
 Boiler Pressure Part Furnace Hanging elements
 Boiler Pressure Part Furnace Hanging elements
Boiler  Flash Tank and Flash Tanks Drain
 PA Fan south of Boiler preparation for installation
B64 STH GL 4-5 ground works 
 B64 STH Deareator installation
 B30 CEB Dry Transformers Installation
 B30 CEB View of West Side
 B30 CEB Cable Trays Erection Lev.0.00
B30 CEB Cable Trays Erection Lev.0.00
 B35 BEB ground beams backfilling View to West
 ESP Steel Erection View to North
 B10 ID Fan Foundation poured
 B17 FGD Outlet View to North
 WFGD Ductworks internal view
 WFGD Absorber embedded ring poured 
 WFGD L07 Service Bldg View to North
 WFGD L04 Pumps Bldg ground beams & backfill in progress 
 E06 CW Blddg Slab poured