18 August, 2015

17.08.15


REBAR CAGE CLEANING IN PROGRESS (B30 WEST)


B63 PILING IN PROGRESS


B01 ZONE A (SOUTH) MANUAL AND HYDRAULIC PILE BREAKING IN PROGRESS
  

B01 ZONE A (NORTH) MANUAL PILE BREAKING IN PROGRESS


EXCAVATION B01 ZONE A (CENTER) IN PROGRESS


16 August, 2015

15.08.15


ARRIVAL OF B01 BOILER EMBEDDED ITEMS 


ARRIVAL OF B01 BOILER EMBEDDED ITEMS 


ARRIVAL OF B01 BOILER EMBEDDED ITEMS 


ARRIVAL OF B01 BOILER EMBEDDED ITEMS 


ARRIVAL OF B01 BOILER EMBEDDED ITEMS 

15 August, 2015

14.08.15


B63 PILE CONCRETING IN PROGRESS


B01 BOILER ZONE A (CENTER) PILE BREAKING STARTED


B01 BOILER ZONE A (NORTH) PILE BREAKING IN PROGRESS


B63 AND B30 PILING IN PROGRESS



B01 BOILER ZONE A (CENTER) PILE BREAKING STARTED


SONIC LOGGING PIPE GROUTING IN PROGRESS (B01 BOILER PILE P095)


REBAR FABRICATION IN PROGRESS

14 August, 2015

13.08.15


B63 AND B30 PILING IN PROGRESS


B01 BOILER ZONE A (SOUTH) FORMATION EXCAVATION IN PROGRESS (@-3.6 M)


B01 BOILER ZONE A (CENTER) FORMATION EXCAVATION IN PROGRESS (@-3.6 M)


B01 BOILER ZONE B (NORTH) FORMATION EXCAVATION STARTED


B01 BOILER ZONE A (NORTH) PILE CUTTING IN PROGRESS


12 August, 2015

11.08.15


PARTIAL EXCAVATION OF B01 BOILER ZONE A (NORTH) STARTED


EXCAVATION OF B01 BOILER ZONE A (SOUTH) IN PROGRESS


PARTIAL EXCAVATION IN THE MIDDLE OF B01 BOILER ZONE A


PILE REBAR CAGE CLEANING IN PROGRESS (B63 TURBINE HALL)


B63 AND B30 PILING IN PROGRESS


B63 PILING IN PROGRESS

11 August, 2015

10.08.15


B30 PILING IN PROGRESS


B01 BOILER ZONE A SOUTH EXCAVATION STARTED.


FINALIZATION OF B01 BOILER ZONE C FIRST PHASE EXCAVATION 


B01 BOILER ZONE A (NORTH) EXCAVATION AND PILE CUTTING
  

TOWER CRANE MAST - STACKING IN PROGRESS

08 August, 2015

07.08.15


B30 PILING IN PROGRESS


B63 PILE CONCRETING IN  PROGRESS


TOWER CRANE (NORTH) FOUNDATION CAPPING COMPLETED.


TRIAL PILE BREAKING ON B35 PILE. 


MANUAL PILE BREAKING IN B01 BOILER ZONE A IN PROGRESS


MC CW PILING IN PROGRESS