30 July, 2015

30.07.15


B63 PILING WORKFRONT FROM THE EAST


B63 TOWER CRANE (NORTH) MAIN BOOM ERECTION COMPLETED. INSTALLATION PENDING


B63 TOWER CRANE (NORTH) PILOT FRAME INSTALLATION IN PROGRESS


INSTALLATION OF TELESCOPING FRAME



PILE CONCRETING IN B63 TURBINE HALL


B01 ZONE A EXCAVATION AND PILE BREAKING


EXCAVATION IN B01 ZONE C


B01 ZONE D PA/FD FAN PILING IN PROGRESS


B01 ZONE D PA/FD FAN PILE CONCRETING IN PROGRESS

29.07.15


B63 PILING IN PROGRESS (NW VIEW)


BORING IN PROGRESS B01 ZONE D


CONCRETING OF PILE IN B01 ZONE D


BACKFILLING OF LAYDOWN AREA IN PROGRESS


BOILER ZONE A FINAL EXCAVATION IN PROGRESS


B63 PILING IN PROGRESS


29 July, 2015

28.07.15


B63 PILING IN PROGRESS


BORING IN PROGRESS IN BOILER ZONE D


START OF FINAL EXCAVATION IN B01 BOILER ZONE A 


PREPARATION WORKS FOR TOWER CRANE ERECTION


28 July, 2015

27.07.15


PILING IN B63 IN PROGRESS



PANORAMIC VIEW OF WORK FRONTS FROM NORTHEAST


BOILER ZONE D PILING IN PROGRESS


REBAR FABRICATION IN PROGRESS IN FABRICATION YARD.







25 July, 2015

24.07.15



PILE REBAR CAGE INSTALLATION IN B35 


B35 PILING IN PROGRESS


B63 PILING IN PROGRESS


REBAR CAGE CLEANING IN PROGRESS


B01 ZONE C EXCAVATION (FIRST 2.0 METERS) IN PROGRESS



VIEW OF WORKFRONT FROM SOUTHEAST


REPAIR OF 1 NOS. BORING RIG IN PROGRESS

24 July, 2015

23.07.15


REBAR FABRICATION IN PROGRESS


B35 AND CW PILING IN PROGRESS


B63 PILE REBAR INSTALLATION


B63 PILE CONCRETING IN  PROGRESS



B01 ZONE C EXCAVATION IN PROGRESS


1 NO. PILE RIG UNDER REPAIR.

23 July, 2015

22.07.15


B30 PILING PLATFORM COMPLETED


CASTING OF TOWER CRANE FOUNDATION (WEST OF B63 TURBINE HALL)


B35 PILING IN PROGRESS


TRIAL FOR PILE BREAKER IN PROGRESS. 


EXCAVATION OF B01 ZONE C IN PROGRESS.

22 July, 2015

21.07.15





PILE CONCRETING IN B63 TURBINE HALL


RAIN AFTERMATH IN WORK FRONT (FROM NORTHEAST) 


EXCAVATION OF B30 PILING ACCESS IN PROGRESS

  

REBAR CAGE INSTALLATION IN PROGRESS


21 July, 2015

20.07.15


VIEW OF THE WORK FRONT FROM WEST OF B63


START OF PILING IN B35 BOILER ELECTRICAL BUILDING



PILE CAGE INSTALLATION IN B63



START OF B30 CENTRAL ELECTRICAL BUILDING EXCAVATION


REBAR INSTALLATION FOR TOWER CRANE FOUNDATION + EMBEDMENT.


PILE REBAR CAGE FABRICATION IN PROGRESS