1x600MW ULTRA SUPER CRITICAL LIGNITE POWER PLANT
31 August, 2015
28.08.15
BOILER AREA – VIEW FROM CENTRE TO WEST
BOILER ZONE A – LEAN CONCRETING & PILE HEAD DEMOLITION IN PROGRESS
BOILER ZONE A – PILE CAP A4 –START OF REINFORCEMENT PLACING
PILING ACTIVITY AT B30 AREA
PILE INTEGRITY TESTING AT BOILER ZONE A
28 August, 2015
27.08.15
COMPLETION OF B63 PILING
BORING B30 PILE
BOILER ZONE A – PILE HEAD DEMOLITION IN PROGRESS
BOILER ZONE B – EXCAVATION & PILE HEAD DEMOLITION IN PROGRESS
REINFORCEMENTS PREFABRICATION FOR BOILER FOUNDATION AREA A
REBAR PREFABRICATION FOR PILING
27 August, 2015
26.08.15
BOILER AREA A & B – VIEW FROM SW
BOILER ZONE A (NORTH) - PILE INTEGRITY TEST IN PROGRESS
BOILER ZONE B (CENTRE) – EXTENSION OF LEAN CONCRETE ON 25/08/15
PILING ACTIVITY AT POWER BLOCK AREA
BORING B63 PILE
POURING B30 PILE
25.08.15
BOILER AREA A – LEAN CONCRETING & EXCAVATION IN PROGRESS
BOILER AREA A & B – VIEW FROM SOUTH
BOILER AREA B (NORTH)
BOILER AREA B (SOUTH- CENTRE)
PILING ACTIVITY AT B30 & B63 AREA
BORING PILE AT B63 AREA
BORING PILE AT B30 AREA
26 August, 2015
24.08.15
PILING ACTIVITY AT POWER BLOCK AREA
BOILER ZONE A – VIEW FROM SOUTH
BOILER ZONE B (NORTH)– LEAN CONCRETE ON 22/08/15
REBAR PREFABRICATION AREA FOR FOUNDATIONS
REBAR PREFABRICATION AREA FOR PILING
21.08.15
BOILER ZONE A
BOILER ZONE A (CENTRE)– EXCAVATION & PILE HEAD BREAKING IN PROGRESS
BOILER ZONE A (SOUTH) LEAN CONCRETE
ON 20/08/15
BOILER ZONE B (NORTH)– EXCAVATION & MANUAL PILE BREAKING IN PROGRESS
BORING B63 PILE
BORING B30 PILE
20.0815
PILING ACTIVITY AT POWER BLOCK AREA
B
OILER ZONE A (NORTH) LEAN CONCRETE & MANUAL PILE BREAKING IN PROGRESS
BOILER ZONE A (CENTRE) LEAN CONCRETE & MANUAL PILE BREAKING IN PROGRESS
BOILER ZONE A (SOUTH) MANUAL PILE BREAKING IN PROGRESS
BOILER ZONE B (NORTH)
MANUAL PILE BREAKING IN PROGRESS
BORING B30 PILE
STEEL CAGE PLACING
B30 PILE
POURING B30 PILE
20 August, 2015
19.08.15
REBAR PREPARATION/CLEANING IN B63
B01 BOILER ZONE A (NORTH) WORK FRONT. LEAN CONCRETE EXTENDED ON THE 18/08/15
B01 BOILER ZONE A (CENTER) LEAN CONCRETING STARTED ON THE 18/08/15
B30 PILING IN PROGRESS
INITIAL PILE BREAKING IN ZONE B (NORTH) IN PROGRESS
19 August, 2015
18.08.15
MINOR EXCAVATION IN B01 ZONE A (CENTER) IN PROGRESS
REBAR CAGE FABRICATION IN NAWARAT/BAUER FABRICATION YARD IN PROGRESS.
SENIOR MANAGEMENT SITE VISIT - WALKDOWN THROUGHOUT WORK FRONTS
SENIOR MANAGEMENT SITE VISIT
SENIOR MANAGEMENT SITE VISIT
SENIOR MANAGEMENT SITE VISIT
SENIOR MANAGEMENT SITE VISIT