31 August, 2015

28.08.15


BOILER AREA – VIEW FROM CENTRE TO WEST


BOILER ZONE A – LEAN CONCRETING & PILE HEAD DEMOLITION IN PROGRESS


BOILER ZONE A – PILE CAP A4 –START OF REINFORCEMENT PLACING 


PILING ACTIVITY AT B30 AREA


PILE INTEGRITY TESTING AT BOILER ZONE A


28 August, 2015

27.08.15


COMPLETION OF B63 PILING 


BORING B30 PILE


BOILER ZONE A – PILE HEAD DEMOLITION IN PROGRESS


BOILER ZONE B – EXCAVATION & PILE HEAD DEMOLITION IN PROGRESS


REINFORCEMENTS PREFABRICATION FOR BOILER FOUNDATION AREA A


REBAR PREFABRICATION FOR PILING

27 August, 2015

26.08.15



BOILER AREA A & B – VIEW FROM SW


BOILER ZONE A (NORTH) - PILE INTEGRITY TEST IN PROGRESS



BOILER ZONE B (CENTRE) – EXTENSION OF LEAN CONCRETE ON 25/08/15



PILING ACTIVITY AT POWER BLOCK AREA



BORING B63 PILE


POURING B30 PILE

25.08.15


BOILER AREA A – LEAN CONCRETING & EXCAVATION IN PROGRESS


BOILER AREA A & B – VIEW FROM SOUTH


BOILER AREA B (NORTH)


BOILER AREA B (SOUTH- CENTRE) 


PILING ACTIVITY AT B30 & B63 AREA


BORING PILE AT B63 AREA


BORING PILE AT B30 AREA

26 August, 2015

24.08.15


PILING ACTIVITY AT POWER BLOCK AREA 


BOILER ZONE A – VIEW FROM SOUTH


BOILER ZONE B (NORTH)– LEAN CONCRETE ON 22/08/15


  REBAR PREFABRICATION AREA FOR FOUNDATIONS


REBAR PREFABRICATION AREA FOR PILING

21.08.15


BOILER ZONE A 


BOILER ZONE A (CENTRE)– EXCAVATION & PILE HEAD BREAKING IN PROGRESS


BOILER ZONE A (SOUTH) LEAN CONCRETE  ON 20/08/15


BOILER ZONE B (NORTH)– EXCAVATION & MANUAL PILE BREAKING IN PROGRESS


BORING B63 PILE 


BORING B30 PILE  

20.0815

PILING ACTIVITY AT POWER BLOCK AREA

BOILER ZONE A (NORTH) LEAN CONCRETE & MANUAL PILE BREAKING IN PROGRESS
BOILER ZONE A (CENTRE) LEAN CONCRETE & MANUAL PILE BREAKING IN PROGRESS

BOILER ZONE A (SOUTH) MANUAL PILE BREAKING IN PROGRESS


BOILER ZONE B (NORTH)  MANUAL PILE BREAKING IN PROGRESS


BORING B30 PILE 

 STEEL CAGE PLACING B30 PILE

POURING B30 PILE

20 August, 2015

19.08.15


REBAR PREPARATION/CLEANING IN B63 


B01 BOILER ZONE A (NORTH) WORK FRONT. LEAN CONCRETE EXTENDED ON THE 18/08/15


B01 BOILER ZONE A (CENTER) LEAN CONCRETING STARTED ON THE 18/08/15


B30 PILING IN PROGRESS


INITIAL PILE BREAKING IN ZONE B (NORTH) IN PROGRESS


19 August, 2015

18.08.15


MINOR EXCAVATION IN B01 ZONE A (CENTER) IN PROGRESS


REBAR CAGE FABRICATION IN NAWARAT/BAUER FABRICATION YARD IN PROGRESS.  


SENIOR MANAGEMENT SITE VISIT - WALKDOWN THROUGHOUT WORK FRONTS


SENIOR MANAGEMENT SITE VISIT 


SENIOR MANAGEMENT SITE VISIT 


SENIOR MANAGEMENT SITE VISIT 


SENIOR MANAGEMENT SITE VISIT