MMO - SITE MANAGEMENT EHS WALK DOWN
BOILER MAIN COLUMNS IN POSITION
READY FOR FINAL PREPARATIONS BEFORE START OF ERECTION
BOILER - VIEW SOUTH TO NORTH - UG NETWORK UNDER CONSTRUCTION
BOILER - VIEW SOUTH TO NORTH
ZONE B - COMPLETE - B/FILL IN PROGRESS
BOILER - VIEW SOUTH TO NORTH
ZONE D - SSC 50% COMPLETE - B/FILL IN PROGRESS
BOILER - VIEW EAST
SS ERECTION PREPARATIONS
STEAM TURBINE HALL - VIEW NORTH
CW PIPE SECTION AND GENERAL PILE HEAD PREPARATION & LEAN CON
STEAM TURBINE HALL - VIEW SOUTH WEST
CW PIPE SECTION AND GENERAL PILE HEAD PREPARATION & LEAN CON
STEAM TURBINE HALL - VIEW NORTH WEST
CW PIPE SECTION AND GENERAL PILE HEAD PREPARATION & LEAN CON
STEAM TURBINE HALL - VIEW NORTH
CW PIPE SECTION AND GENERAL PILE HEAD PREPARATION & LEAN CON
.
EXAMPLE OF MAIN SITE ACCESS ROADS
EXTERNAL LAYDOWNS - BOILER PREFAB AREA
- TEMPORARY ROADS & ACCESS UNDER CONSTRUCTION