VIEW TO EAST OVER STH EXCAVATION TO BOILER.
VIEW TO NORTH OVER COAL BUNKER & MILL BAY
BOILER AREA READY FOR MECHANICAL ERECTION
- INSTALLATION OF CRANE MATS
MORNING COORDINATION MEETING - BOILER AREA
B02 - STACK - SLIP FORM SYSTEM UNDER FABRICATION
B02 - STACK - FINAL PREPARATIONS BEFORE CASTING WK 51
B02 - STACK - FINAL PREPARATIONS BEFORE CASTING WK 51
L05 - WFGD ABSORBER TOWER FOUNDATION - REBAR IN PROGRESS
CW PIPING COFFERDAM VIEW WEST
B01 - 50 TON TOWER CRANE - FOUNDATION CAST
AND READY FOR CTO BACK TO MECHANICAL ERECTOR
CW PIPING COFFERDAM VIEW WEST
B63 STH / CWP - PIPE FIT UP IN PROGRESS
B63 STH - REBAR & FORMWORK IN PROGRESS
FOR FIRST TWO POURS - WK 51
B63 STH - REBAR & FORMWORK IN PROGRESS
FOR FIRST TWO POURS - WK 51