B01 - 1ST MAIN STRUCTURE STEEL COLUMN
FINAL PREPARATIONS
TANDEM LIFT SET UP TO "TOP & TAIL" THE PIECE
THE MAIN CRANE (GREEN) IS A 250 TON &
THE THE TAILING CRANE (WHITE) IS A 80 TON
CAPACITY CRAWLER TYPE.
B01 - 1ST MAIN STRUCTURE STEEL COLUMN
FINAL PREPARATIONS
TRADITIONAL THAI BLESSING FOR A SAFE & SUCCESSFUL WORKS
BOILER AREA BACK FILLING &
PREPARATIONS CONTINUE IN PARALLEL
FINAL SET & RIGGING CHECK ON THE LOAD BEFORE LIFTING
START OF TAILING LIFT
COLUMN FREE OF TAILING CRANE AND OVER FINAL POSITION
AERIAL SHOT VIEW FROM SOUTH TO NORTH WEST
AERIAL SHOT VIEW FROM SOUTH TO NORTH
AERIAL SHOT VIEW FROM EAST TO WEST
COLUMN IN FINAL POSITION AND TEMPORARY SUPPORT
WIRES UNDER INSTALLATION
COLUMN IS RELEASED FROM 250 TON CRANE
AND FULLY SELF SUPPORTED
OPERATION COMPLETE AND TEAM MOVE TO THE NEXT PIECE.
wow, great, I was wondering how to cure acne naturally. and found your site by google, learned a lot, now i’m a bit clear. I’ve bookmark your site and also add rss. keep us updated.
ReplyDeletenew boiler cost
The condensate recovery system used to capture and return condensate to the boiler – this comprises steam traps and piping along with vessels used to store the condensate before it is pumped.
ReplyDeleteboiler heating treatment Company in Ontario