06 April, 2017

06-04-17

F05 - 230kV Swyr Substation view from South
F05 - 230kV Swyr Substation and B68 Transformer Area view from South
Swyr - Transformer and STH South-West view
F05 - 115kV Swyr Substation view from South-West
Fire Fighting water system pipes installation Swyr - Transformer Area
B68 - Transformer Area view from North-West side
B68 - SST Transformer Erection
F05 - 115kV Swyr Substation view from West
B68 - Transformer Area view from CEB - West side
F05 - 230kV Swyr Substation view from ECB
F05 - 115kV Swyr Substation view from ECB
B68 - Transformer Area view from CEB - East side
B63 - STH West side view from ECB
Oily water tank for transformer Area installation
B30 - CEB North side external area view - Cable trays erection
B30 - CEB East side external area view - Fire Deluge system erection
C01 - Fuel oil Tank erection - West view
C01 - Fuel oil Tank erection - South-East view
B30 - CEB +4.00m MV Room erection activities
B30 - CEB +4.00m MV Room erection activities
B30 - CEB  +4.00m Battery Room erection activities
B30 - CEB +4.00m LV Room erection activities
B30 - CEB +4.00m LV Room erection activities
B30 - CEB +4.00m LV Room erection activities
B30 - CEB +4.00m LV Room erection activities
B30 - CEB +11.00m Control Room erection activities
B30 - CEB +11.00m Control Room erection activities
B30 - CEB +11.00m Control Room erection activities
B30 - CEB +11.00m Control Room erection activities
B30 - CEB +11.00m LV Room erection activities
B30 - CEB +11.00m LV Room erection activities
B33 - CEB +16.00m Main Control Room Area erection activities
B33 - CEB +16.00m Main Control Room area erection activities
B33 - CEB +16.00m Main Control Room area erection activities
B63 - STH Piping erection activities
B63 - STH CCW pump erection activities
B63 - STH B20 Condenser extraction pumps erection
B63 - STH B20 Condenser extraction pumps erection
B63 - STH GEN Cooling /  Sealing auxiliary erection
B63 - STH GEN Cooling / Sealing auxiliary erection
B64 - STG GEN Stator ready for lifting activities
B95 - Condensate Polishing  Plant construction
B01 - Boiler South-East side view
B01 - Boiler North-East side view
B01 - Boiler pressure parts erection
B01 - Boiler pressure parts erection
B01 - Boiler ducts erection
B07 -  ESP South-West view
B07 -  ESP South-West side view
B07 -  ESP South-West side view
B07 -  ESP North-East side view
B07 -  ESP North-West side view
B07 -  ESP and B01 Boiler North-East side view
ESP & NH3 Storage tank South side view
G21 -  NH3 Storage Tank - Bluilding Construction
L10 -  WFGD Booster Fans Bldg. South side view
E04 -  Cooling Tower - South side view
E12 -  Circulating water pumps erection
E12 -  Circulating water pumps erection
G07 & G02 Water tanks Erection
L10 -  WFGD Booster Fans Bldg. East side view
L07 - FGD Service Building construction
L05 -  WFGD Absorber / Reactor tower erection
L06 - FGD Electrical Building construction
L10 -  WFGD Booster Fans Bldg. North side view
WFGD Area North-East side view

L04 -  WFGD Pump Bldg. East side view
D20 - Fly Ash Compressor Bldg.Construction
D07 - Slag conveyors construction