29 May, 2017

29-05-17

F05 - 230 kV Swyr. Substation view from Boiler
B01 - Boiler Roofing erection activities
B01 - Boiler Roofing erection activities
B01 - Boiler Roofing erection activities
B01 - Boiler Roofing erection activities
B01 - Boiler Roofing erection activities
B01 - Boiler Roofing erection activities
B01 - Boiler Furnace Bottom Front assembly activities
B01 - Boiler Furnace Bottom Front assembly activities
B01 - Boiler Furnace Bottom Rear assembly activities
B01 - Boiler Furnace Bottom Rear assembly activities
B01 - Boiler Furnace Bottom Rear assembly activities
B01 - Boiler Furnace Bottom Front assembly activities
B01 - Boiler Furnace Bottom Rear assembly activities
B01 - Boiler Furnace Bottom assembly activities
B01 - Boiler Furnace Bottom Rear assembly activities
B01 - Boiler Pressure Parts erection activities
B01 - Boiler Pressure Parts erection activities
B01 - Boiler Pressure Parts - Piping erection activities
B01 - Boiler Pressure Parts - Piping erection activities
B01 - Boiler Pressure Parts - Piping erection activities
B01 - Boiler Pressure Parts - Piping erection activities
B01 - Boiler Pressure Parts erection activities
B01 - Boiler ducts erection activities
B01 - Boiler piping erection activities
B01 - Boiler Piping erection activities
B01 - Boiler ducts erection activities
B01 - Boiler Ducts insulation activities
B01 - Boiler Fans erection activities
Temporary discharge pit construction for Boiler & WSC hydrotest
B01 - Boiler temporary tower crane erection activities - South side
B63 - STH Condenser water boxes prepare for CW pipes connection
B63 - STH Condenser water boxes prepare for CW pipes connection
B63 - STH Condenser water boxes prepare for CW pipes connection
B63 - STH Condenser water boxes prepare for pipes connection
B95 - Condensate Polishing Plant access platform stair erection
B95 - Condensate Polishing Plant Civil works activities
B95 - Condensate Polishing Plant prepare foundation for equipment erection
B63 - Condenser Vacuum Pump erection
B63 - Condenser Vacuum Pump erection
B63 - Condenser Vacuum Pump erection
G08 - Compressed Air Production Bldg. Construction view from Boiler