13 May, 2015
11 May, 2015
07 May, 2015
07.05.15
BAUER PILING COMMENCE PILING IN BOILER ZONE A
"21.05M LONG PILES" EAST (MILLS & EAST SIDE OF FURNACE)
PILING BALANCE OF WFGD ANCILLARY TANK FOUNDATIONS
INSTALLING CAGE ON BOILER ZONE A (P247)
BORING BOILER ZONE A PILES (P349)
CASTING WFGD UNIT L39 PILES
CASTING LAST WFGD UNIT L39 PILE (L39-3)
TRIAL MIX RUNS ON SITE BATCHING PLANT UNIT 2
(UNIT 1 OPERATIONAL & SUPPLYING SITE)
05 May, 2015
05.05.15
PREFABRICATION OF B01 BOILER "LONG" 21.05M PILES
WFGD TANK PILES
STRIKING OF MLT RIG OFF B63 STH TP-B17 TO PREPARE FOR LATERAL TEST
BAUER PILE REBAR CAGE PREFABRICATION
SITE BATCHING PLANT UNIT 2 READY FOR TRIAL MIX
SITE BATCHING PLANT UNIT 1 IS OPERATIONAL
- FIRST CONCRETE DELIVERED 2ND MAY 2015
SITE BATCHING PLANT UNIT 1 IS OPERATIONAL
- FIRST CONCRETE DELIVERED 2ND MAY 2015
NO WORKS BY CLIENT B/FILL CONTRACTOR DUE TO PUBLIC HOLIDAY
04.05.15
GENERAL SITE VIEW OF PILING OPERATION
BORED PILING ON LAST OF BOILER ZONE C 14.05M "SHORT" PILES
LIGNITE STRATA FOUND ON BOILER ZONE C PILES
CASTING PILES
INSTALLATION OF REBAR CAGES ON WFGD Lxx ANCILLARY TANK FOUNDATIONS
INSTALLATION OF SONIC LOGGER TUBES ON BOILER ZONE C SHORT PILE P164
LATERAL TEST ON B63 STH TP-B14
HEAVY RAIN AND WINDS FROM 1600HRS