06 March, 2015

03.03.15

SITE VIEW FROM SOUTH
   

 WEEKLY SAFETY INDUCTION CONTINUE REGULARLY EVERY TUESDAY

 PREPARATION WORK FOR AXIAL TENSILE LOAD TEST ON TPB13


 TPB15 READY FOR MAINTAINED LOAD TEST

 START OF MAINTAINED LOAD TEST ON PILE TPB15

 PREPARATION WORK FOR MAINTAINED LOAD TEST ON TPB18

 TPB18- PLACING HYDRAULIC  JACKS UNDER REACTION GIRDER

 PILING WORK FOR MC’S TEST PILES ONGOING

 FENCING AT SOUTH SIDE IN GOOD PROGRESS

PREPARATION OF AREA FOR CONSTRUCTION OF SITE BATCHING PLANT BY CPAC