05.03.15

 SITE SITUATION TODAY -VIEW FROM EAST

 ALSTOM MANAGEMENT SITE VISIT

 AXIAL TENSILE LOAD TEST ON TPB13 ONGOING

 TENSILE LOAD TEST ON TPB13 – HONEY BOX

 MAINTAINED LOAD TEST ON TPB15 IN PROGRESS

 TPB15 - HYDRAULIC  JACKS UNDER REACTION GIRDER

 PREPARATION WORK ON TPB18 FOR MAINTAINED LOAD TEST

PILING WORK FOR MC’S TEST PILES 

 FENCING AT SOUTH-WEST SIDE WILL BE CONTINUED AFTER LAND RECLAMATION

CONSTRUCTION OF SITE BATCHING PLANT BY CPAC ON GOING