31 March, 2015

23.03.15

 BATCHING PLANT UNIT 1 - INSTALLING WATER PIPING
                             UNIT 2 -  INSTALLING LOADER RAMP

 PILE HEAD & AREA PREPARATION FOR TP-B01 TESTING

ADDING BALLAST TO COMPRESSION TEST RIG ON TP-B05 

                       COMPRESSION TEST CONTINUES ON TP-B06                                  

COMPRESSION TEST CONTINUES ON TP-B08 

TENSION TESTING ON TP-12 (MC)

CLIENT B/FILL CONTINUES ON SOUTH BOUNDARY OF MAIN SITE