31 October, 2015

30.10.15


WORKS PROGRESSING ON PILECAP B1 ZONE B


PEDESTAL PREPARATION IN ZONE A


PRE CONCRETING CHECKS IN B01 BOILER ZONE A 


PRE CONCRETING CHECKS IN B01 BOILER ZONE A 

30 October, 2015

29.10.15


ZONE C PILECAP C6 PRE CONCRETING INSPECTION IN PROGRESS 


TJEL LAYDOWN - CW PIPES STORAGE


TJEL LAYDOWN FOR SS SECTIONS < 25t


PILECAP B3 ZONE B FORMWORKS INSTALLATION IN PROGRESS 


MC PILING WORKFRONT IN PROGRESS


CONCRETING OF PILECAP C6 ZONE C

29 October, 2015

28.10.15


COAL MILL PREPARATION UNDERWAY


LIFT PIT PREPARATION WORKS UNDERWAY


ZONE B WORKFRONT IN PROGRESS


ZONE A PEDESTAL PRE CONCRETING CHECKS IN PROGRESS


ZONE A PEDESTAL PRE CONCRETING CHECKS IN PROGRESS

28 October, 2015

27.10.15


COAL MILL 1 TEMPORARY WORKS SETUP 



PILECAP B3 (SOUTH)



PILECAP C11 CONCRETING IN PROGRESS



ZONE C WORKFRONT IN PROGRESS

27 October, 2015

26.10.15


B64 TEST PILES (ANCHOR PILE) INSTALLATION


ZONE A WORKFRONT (WEST)


PEDESTAL REBAR INSTALLATION ON PILECAP B1


PILECAP A5 READY FOR INSPECTION

24 October, 2015

23.10.15



FORMWORK INSTALLATION PILECAP B3 (EAST)


PILECAP C11 FORMWORK INSTALLATION IN PROGRESS


FORMATION LEVEL EXCAVATION AND LEAN CONCRETING IN PROGRESS
  

ZONE C WORKFRONT IN PROGRESS

23 October, 2015

22.10.15


PILECAP B3 (NORTH) CONCRETING


PILECAP B3 (NORTH) CONCRETING


PEDESTAL FORMWORK INSTALLATION IN PROGRESS


PILECAP A5 IN PROGRESS
  

ZONE C WORKFRONT IN PROGRESS

22 October, 2015

21.10.15


PILECAP B3 (NORTH) FORMWORK INSTALLATION


INSTALLATION B64 TEST PILES IN PROGRESS


SURFACE PATCH-UP/ REPAIRS IN PROGRESS


PILE HACKING OF FINAL 2 PILES IN ZONE B


ZONE C REBAR AND FORMWORKS IN PROGRESS 


INSTALLATION B64 TEST PILES IN PROGRESS


CW PIPE SADDLES IN PROGRESS

21 October, 2015

20.10.15


PILECAP B3 (SOUTH) REBAR INSTALLATION IN PROGRESS


PRE- POUR INSPECTION FOR ANCHOR BOLTS ZONE A


PRE- POUR INSPECTION FOR ANCHOR BOLTS ZONE A


REBAR INSTALLATION PILECAP A5


REBAR AND FORMWORK INSTALLATION ZONE C




20 October, 2015

19.10.15


PILECAP ZONE B SOUTH - CONTINUATION OF REBAR INSTALLATION


PILECAP C19 READY FOR CONCRETING


PILECAP C5 READY FOR CONCRETING


B64 PILING COMPLETED (18/10/15) 

18 October, 2015

17.10.15




AERIAL VIEW WEST


AERIAL VIEW WEST


AERIAL PLAN VIEW


AERIAL PLAN VIEW


CW AREA AND CONTRACTORS YARD


BOILER (VIEW FROM EAST)


WORKFRONT VIEW (SOUTH)


PRE-CONCRETING INSPECTION PEDESTALS ZONE A


PRE-CONCRETING INSPECTION PEDESTALS ZONE A