1x600MW ULTRA SUPER CRITICAL LIGNITE POWER PLANT
31 October, 2015
30.10.15
WORKS PROGRESSING ON PILECAP B1 ZONE B
PEDESTAL PREPARATION IN ZONE A
PRE CONCRETING CHECKS IN B01 BOILER ZONE A
PRE CONCRETING CHECKS IN B01 BOILER ZONE A
30 October, 2015
29.10.15
ZONE C PILECAP C6 PRE CONCRETING INSPECTION IN PROGRESS
TJEL LAYDOWN - CW PIPES STORAGE
TJEL LAYDOWN FOR SS SECTIONS < 25t
PILECAP B3 ZONE B FORMWORKS INSTALLATION IN PROGRESS
MC PILING WORKFRONT IN PROGRESS
CONCRETING OF PILECAP C6 ZONE C
29 October, 2015
28.10.15
COAL MILL PREPARATION UNDERWAY
LIFT PIT PREPARATION WORKS UNDERWAY
ZONE B WORKFRONT IN PROGRESS
ZONE A PEDESTAL PRE CONCRETING CHECKS IN PROGRESS
ZONE A PEDESTAL PRE CONCRETING CHECKS IN PROGRESS
28 October, 2015
27.10.15
COAL MILL 1 TEMPORARY WORKS SETUP
PILECAP B3 (SOUTH)
PILECAP C11 CONCRETING IN PROGRESS
ZONE C WORKFRONT IN PROGRESS
27 October, 2015
26.10.15
B64 TEST PILES (ANCHOR PILE) INSTALLATION
ZONE A WORKFRONT (WEST)
PEDESTAL REBAR INSTALLATION ON PILECAP B1
PILECAP A5 READY FOR INSPECTION
24 October, 2015
23.10.15
FORMWORK INSTALLATION PILECAP B3 (EAST)
PILECAP C11 FORMWORK INSTALLATION IN PROGRESS
FORMATION LEVEL EXCAVATION AND LEAN CONCRETING IN PROGRESS
ZONE C WORKFRONT IN PROGRESS
23 October, 2015
22.10.15
PILECAP B3 (NORTH) CONCRETING
PILECAP B3 (NORTH) CONCRETING
PEDESTAL FORMWORK INSTALLATION IN PROGRESS
PILECAP A5 IN PROGRESS
ZONE C WORKFRONT IN PROGRESS
22 October, 2015
21.10.15
PILECAP B3 (NORTH) FORMWORK INSTALLATION
INSTALLATION B64 TEST PILES IN PROGRESS
SURFACE PATCH-UP/ REPAIRS IN PROGRESS
PILE HACKING OF FINAL 2 PILES IN ZONE B
ZONE C REBAR AND FORMWORKS IN PROGRESS
INSTALLATION B64 TEST PILES IN PROGRESS
CW PIPE SADDLES IN PROGRESS
21 October, 2015
20.10.15
PILECAP B3 (SOUTH) REBAR INSTALLATION IN PROGRESS
PRE- POUR INSPECTION FOR ANCHOR BOLTS ZONE A
PRE- POUR INSPECTION FOR ANCHOR BOLTS ZONE A
REBAR INSTALLATION PILECAP A5
REBAR AND FORMWORK INSTALLATION ZONE C
20 October, 2015
19.10.15
PILECAP ZONE B SOUTH - CONTINUATION OF REBAR INSTALLATION
PILECAP C19 READY FOR CONCRETING
PILECAP C5 READY FOR CONCRETING
B64 PILING COMPLETED (18/10/15)
18 October, 2015
17.10.15
AERIAL VIEW WEST
AERIAL VIEW WEST
AERIAL PLAN VIEW
AERIAL PLAN VIEW
CW AREA AND CONTRACTORS YARD
BOILER (VIEW FROM EAST)
WORKFRONT VIEW (SOUTH)
PRE-CONCRETING INSPECTION PEDESTALS ZONE A
PRE-CONCRETING INSPECTION PEDESTALS ZONE A