29 October, 2015
28.10.15
COAL MILL PREPARATION UNDERWAY
LIFT PIT PREPARATION WORKS UNDERWAY
ZONE B WORKFRONT IN PROGRESS
ZONE A PEDESTAL PRE CONCRETING CHECKS IN PROGRESS
ZONE A PEDESTAL PRE CONCRETING CHECKS IN PROGRESS