02.10.15
WORKFRONT VIEW (SOUTH)
PILECAP B3 REBAR INSTALLATION IN PROGRESS
CEX 1ST CASING IN THE GROUND. B64 PILING STARTED.
PREPARATION FOR PEDESTAL CONCRETING IN ZONE A IN PROGRESS (I.E. ROUGHENING, BOLT INSTALLATION ETC)