29 November, 2015

28.11.15

    B63 - view SE - excavation to final level, lean con and pile trimming. 
    Boiler  - view NE - 50T tower crane preparations 
    Boiler South side Back filling & preparations for steel erection
    Boiler South Side - preparations for steel erection 
    Boiler - South Side - Zone B - b/fill in progress.
    B64 - view SW - Test piles - Tension Test
    B64 - view South - Test piles - Tension Test
    B63 - view North - PDA testing on B64 piles and excavation. 







21 November, 2015

20.11.15


MCW LINE (NORTH WEST)


B63 AND MCW WORKFRONT (NORTH)


B63 TERS AND EXCAVATION IN PROGRESS (SOUTH)


OVERVIEW OF B63 AND B01 WORKFRONTS (SOUTH)


B01 WORKFRONT (SOUTH WEST)


B01 WORKFRONT (WEST)


CLOSE-UP ON MCW LINE


AERIAL SHOT OF B01 AND B63


AERIAL SHOT OF B01 AND B63


PAN VIEW OF SITE (SOUTH)


PAN VIEW OF SITE (SOUTH EAST)


B02 STACK AREA


PAN VIEW OF SITE (EAST)


PAN VIEW OF TJEL LAYDOWN AREA


PAN VIEW OF TJEL LAYDOWN AREA


OVERVIEW OF WHOLE LAYDOWN AREA (TJEL + NAWARAT)


VIEW OF RETENTION/DRAINAGE POND (EAST)


PAN VIEW OF COOLING TOWER AND REBAR FABRICATION YARD (EAST) 






B63 TERS WORK IN PROGRESS



KENTLEDGE INSTALLATION FOR B64 LOAD TEST IN PROGRESS



BACKFILLING AND COMPACTION FOR B01 BOILER ZONE A (SOUTH) IN PROGRESS



SSC REBAR INSTALLATION IN PROGRESS



PRE-CONCRETING CHECKS ON BOILER ZONE C PEDESTALS IN PROGRESS



PRE-CONCRETING CHECKS ON BOILER ZONE C PEDESTALS IN PROGRESS

20 November, 2015

19.11.15

.

B63 TERS IN PROGRESS


INITIAL PRE-FORMWORKS CHECKS ON COAL MILL 7 


BACKFILLING OF B01 ZONE A (SOUTH) IN PROGRESS


H02 ELECTRICAL PULLPITS FOR BOILER AREA IN PROGRESS


SSC REBAR INSTALLATION IN PROGRESS


LEAN CONCRETE AND PILE BREAKING IN B63 IN PROGRESS. 

18 November, 2015

18.11.15

View West from newly cut Client forest area - proposed +100k m2 of lay down

Main Lay down and prefabrication area still under preparation by client

Curing main Bunker Steel Structure Pedestals before protective coating

Boiler Zone D - SSC foundation works in progress 

Final cleaning and touch up of Boiler Main Steel Pedestals before back fill 
Final preparations for remaining 2 No. Coal Mills


Zone B - North - Main Boiler steel - Complete & B/Fill started

Zone B - North - Main Boiler steel - Complete & B/Fill started

Boiler Zone A Coal Mills & Main Steel - UG Network Pit foundations started

Boiler Zone C - Air Pre-heater & FGD Ducts 
- B17 Ducts to ESP in foreground

                                      
B63 STH - Main foundation Excavation & Piles cut to C.O.L on CW pipe section

CW Pipe foundation View East to ACC Plant 

 CW Pipe foundation View West along Boiler