17 November, 2015

17.11.15



PILECAP B3 PEDESTALS READY FOR CONCRETING


PILING OF UEU CONYEYOR PILES (2 NOS.) 


PRE CONCRETING INSPECTION ON PILECAP B3 PEDESTALS


PRE CONCRETING INSPECTION ON PILECAP B3 PEDESTALS


DAMP-PROOFING COATING IN PROGRESS (ZONE B)


PEDESTAL CONRETING (PILECAP B3) IN PROGRESS


TERS IN PROGRESS IN B64